DON’T IGNORE A NOTICE OF CONTEST OF LIEN

A recent case, Jon M. Hall Company, LLC v. Canoe Creek Investments, LLC, 49 Fla.L.Weekly D812a (Fla. 2d DCA 2024), demonstrates four important things when it comes to liens:

  1. An owner can shorten the time period to foreclose on the lien, whether against the real property or a lien transfer bond, to 60 days by recording a notice of contest of lien;
  2. An owner can transfer a lien to a lien transfer bond during litigation;
  3. An owner can record a notice of contest of lien to force the lienor to amend its lawsuit to sue the lien transfer bond surety within 60 days; and
  4. A contractors’ failure to amend its lawsuit to sue the lien transfer bond within 60 days will extinguish its rights to pursue a claim against the lien transfer bond, and will otherwise extinguish the lien, fairly or unfairly.

Here are the key facts in Jon M. Hall Company:

  • 4/14/22 – Contractor recorded claim of lien for $825,639.46
  • 5/17/22 – Owner transferred Contractor’s claim of lien to a lien transfer bond
  • 5/20/22 – Owner recorded a notice of contest of Contractor’s claim of lien
  • Late May 2022 – Contractor recorded amended claim of lien for $1,837,516.76
  • 6/14/22 – Contractor filed lawsuit against Owner including a lien foreclosure as to its amended claim of lien. Contractor did not sure the lien transfer bond surety
  • 7/1/22 – Owner transferred Contractor’s amended claim of lien to a lien transfer bond
  • 7/1/22 – Owner recorded a notice of contest of Contractor’s amended claim of lien
  • Contractor did not amend its lien foreclosure lawsuit to sue the lien transfer bond within 60 days
  • 12/19/22 – Owner moved for partial summary judgment on Contractor’s lien foreclosure lawsuit. “[Owner] asserted that transferring to bond and recorded notices of contest as to both [Contractor’s] Original Claim of Lien and Amended Claim of Lien had shortened the time for [Contractor] to bring action against the bond. [Contractor] had failed to timely do so, thereby resulting in automatic extinguishment of the lien as a matter of law.”
  • Trial court granted Owner’s motion for partial summary judgment holding that “[Owner’s] transfer and recording of the notice of context as to the Amended Claim of Lien during the litigation shortened the time for [Contractor] to bring a claim against the bond to sixty days, and [Contractor’s] failure to timely do so extinguished its lien automatically as a matter of law.”

The Contractor moved for a petition for a writ of certiorari to quash the trial court’s order that held its lien was extinguished as a matter of law.

A lienor has one year under Florida Statute Section 713.22 to foreclose on a claim of lien. This time period may be shortened to 60 days by an owner recording a notice of context of lien under Florida Statute Section 713.24.  The notice of contest statute provides, “[t]he lien of any lienor upon whom such notice is served and who fails to institute a suit to enforce his or her lien within 60 days after service of such notice shall be extinguished automatically.”

Separately, under Florida Statute 713.24, a lien against real property can be transferred to the security of a lien transfer bond which removes the collateral of the lien from the real property to the lien transfer bond.

Construing Florida Statutes 713.22 and 713.24 together, “under the plain statutory language, where a lien is transferred to a bond during litigation, and the owner records a notice of contest, the lienor has “60 days” “within which to commence an action to enforce any claim of lien or claim against a bond,” or else the “lien . . . shall be extinguished automatically.” Jon M. Hall Company, supra (internal citations omitted).

Here, it is true that [Contractor’s] Original Claim of Lien was recorded, transferred, and noticed for contest before the litigation commenced. However, before the June 2022 lawsuit, [Contractor] also recorded an Amended Claim of Lien, more than doubling the amount claimed. [Contractor] thereafter filed its complaint, expressly acknowledging and seeking to recover on the higher Amended Claim of Lien. Two weeks later, [Owner] transferred the Amended Claim of Lien to the bond and recorded its notice of contest thereof, just as it had with the original one.

Thus, after [Contractor] commenced litigation on its Amended Claim of Lien, [Owner’s] actions in transferring the Amended Claim of Lien to bond under section 713.24 and then recording its notice of contest of the Amended Claim of Lien under section 713.22(2) operated to shorten the time period for [Contractor] to bring an action against the surety on the bond to sixty days. 

***

On that question, the statutory language is quite clear: after [Contractor] “commenced” this “proceeding to enforce a lien” expressly seeking to recover on its Amended Claim of Lien, “during such proceeding, the lien [wa]s transferred” by Owner.  When [Owner], as the owner of the property, recorded its notice of contest of the transferred Amended Claim of Lien, that “shorten[ed] the time . . . within which to commence an action to enforce any claim of lien or claim against a bond or other security.”  Contractors failure to seek to claim against the bond within sixty days thereafter caused its lien to “be extinguished automatically” by operation of law. 

***

[Contractor] also asserts that both of [Owner’s] notices of contest of lien were invalid because they were recorded after [Owner] had already transferred the claims of lien to bond. But [Contractor] has not cited, nor have we found, any support for this claim. Indeed, the only case Hall cites for this proposition involved the same order of events, without suggesting there was anything improper about it. 

Jon M. Hall Company, supra (internal citations omitted).

Look, when it comes to claims of lien, do yourself a favor.  Use a construction lawyer.  Use a lawyer that understands liens, and importantly, Florida’s Lien Law.  I cannot emphasize these points enough.  If you don’t, you can get caught with gotcha tactics or crazy nuances under Florida’s Lien Law.  I don’t necessary agree with the holding in this case.  Regardless, when receiving a notice of contest of lien, you need to respect the implications and make sure rights are immediately preserved.  Otherwise, you get caught in the scenario here where a lienor had a $1.8 Million lien extinguished. OUCH!!!

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

HUH? ACTION ON CONSTRUCTION LIEN “RELATES BACK” DESPITE NOTICE OF CONTEST OF LIEN

Not every case law you read makes sense. This sentiment goes to the uncertainty and grey area of certain legal issues.  It is, what you call, “the nature of the beast.”  You will read cases that make you say “HUH?!?” This is why you want to work with construction counsel to discuss procedures and pros / cons relative to construction liens.

An example of a case that makes you say “HUH” can be found in Woolems, Inc. v. Catalina Capstone Creations, Inc., 2023 WL 2777506 (Fla. 3d DCA 2023) dealing with a construction lien foreclosure dispute.

Here, a contractor filed a lawsuit against a subcontractor with a summons to show cause why the subcontractor’s construction lien should not be discharged.  This is a specific complaint filed under Florida Statute s. 713.21(4). This statute requires the lienor to essentially foreclose on its construction lien within 20 days after it was served with a “show cause” summons.  The subcontractor filed its answer and counterclaim but did NOT assert a claim to foreclose its construction lien.

Around the time of subcontractor’s answer and counterclaim, the contractor transferred the subcontractor’s lien to an all-cash lien transfer bond in accordance with Florida Statute s. 713.24. Once the lien transfer bond was recorded, the owner recorded a notice of contest of lien under Florida Statute s. 713.22. The notice of contest of lien shortens the limitations period to foreclose on a lien to 60 days.

The subcontractor did NOT timely foreclose its lien against the lien transfer bond and the general contractor moved to have its all-cash lien transfer bond returned, as it should do. The subcontractor filed its lien foreclosure against the lien transfer bond AFTER the 60-day window expired. The trial court, and affirmed by the appellate court, denied the general contractor’s request to have the lien transfer bond returned and allowed the subcontractor to assert its (dilatory) claim against the lien transfer bond claiming it related back in time to the subcontractor’s initial counterclaim.  HUH?!?

ISSUES GIVING RISE TO THE HUH

Here are the issues with this ruling:

  1. The subcontractor should have foreclosed its construction lien with the 20-day time period from receiving the summons to show cause. The case reflected the subcontractor asserted claims, but not the lien foreclosure claim subject to the summons to show cause. (The appeal did not discuss this point for reasons currently unknown.)
  2. Regardless of (1), the lien was transferred to a bond and a notice of contest of lien was recorded shortening the time period to foreclose the lien (as to the bond) to 60 days. There is case law referencing this procedure. Yet, the subcontractor still did not timely assert its claim against the lien transfer bond.
  3. The trial court applied the relation back doctrine which does nothing but completely water down the statutory purpose of a notice of contest of lien (not to mention the summons to show cause complaint).

RECOMMENDATIONS IN LIGHT OF RULING

In light of this ruling, here are my recommendations:

  1. If you are going to transfer a lien to a lien transfer bond, do it from the get-go. Then, record the notice of contest or pursue the summons to show cause complaint.
  2. If filing the summons to show cause complaint, wait for the 20-day time period to expire. If the time period expires, move to have the lien discharged before making the decision to transfer the lien to a lien transfer bond.
  3. If recording a notice of contest of lien, wait for the 60-day time period to expire before taking action.

The reality is that the procedure implemented in this case should have been fine but for the application of the relation back doctrine that makes you say HUH?!?

As mentioned, if dealing with a lien, please make sure to discuss strategic considerations with a construction counsel that can help navigate the process and advise on the pros and cons.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

QUICK NOTE: THE NOTICE OF CONTEST OF LIEN IS A POWERFUL TOOL

If you receive a Notice of Contest of Lien, do NOT ignore it.  The Notice of Contest of Lien is a powerful tool that shortens the limitations period for a linear to foreclose on a construction lien to 60 days or else the lien is discharged by operation of law.   Conversely, if you receive a construction lien, consider recording a Notice of Contest of Lien based on its utility.

As an example of the usefulness of the Notice of Contest of Lien, in Rabil v. Seaside Builders, LLC, 226 So.3d 935 (Fla. 4th DCA 2017), a contractor filed a construction lien foreclosure lawsuit on a residential project.  The homeowners then transferred the lien to a lien transfer bond and recorded a Notice of Contest of Lien.  The contractor did not amend the lawsuit to sue the lien transfer bond surety within the 60-day window.  Consequently, the homeowners moved to dismiss the lien foreclosure lawsuit, release the lien transfer bond, and discharge the corresponding lis pendens.  The trial court denied the motion.  On appeal, the Fourth District reversed holding that “[b]ecause the contractor did not file suit against the surety within sixty days [in response to the Notice of Contest of Lien], the lien was automatically extinguished by operation of law, and the clerk was obligated to release the bond.” Rabil, 226 So.3d at 937.

This case exemplifies the utility of recording a Notice of Contest of Lien and how it benefitted the homeowner upon filing the Notice of Contest of Lien after recording the lien to a lien transfer bond post-initiation of the lawsuit.  The is exactly why a Notice of Contest of Lien should not be ignored.  If you receive one, the smart play is to immediately consult with counsel, just like the smart play if you receive a construction lien is to consult with counsel.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

QUICK NOTE: A CONSTRUCTION LIEN IS NOT INTENDED TO LAST INDEFINITELY

A construction lien is not intended to last forever.  A construction lien must be foreclosed within one year from its recording date because a construction lien only lasts for one year by operation of law.   You will not be able to foreclose a construction lien after this one-year period expires.  This is why it is always good practice to calendar the expiration of this one-year period when a construction lien is recorded.   There is never a good reason to engage in a last minute scramble to file a foreclosure lawsuit on the expiration date (or shortly before).      While I always believe a lienor should work with counsel to record a construction lien, regardless, I would certainly recommend a lienor to work with counsel to ensure lien rights are properly perfected so that when it becomes necessary to foreclose the lien, the strategy is in place to file the foreclosure lawsuit.

 

Importantly, an owner can shorten the one-year period for a lienor to foreclose its construction lien by properly recording a Notice of Contest of Lien.  A Notice of Contest of Lien will shorten the period for a lienor to foreclose its construction lien to sixty days.   It is always beneficial to record the Notice of Contest of Lien sooner than later because it puts the onus on the lienor to either foreclose the construction lien or lose its lien and ability to foreclose its lien by operation of law.  That’s right – if the lienor does not foreclose its lien within the sixty-day window, it will have lost its lien rights.   There are times where an owner of real property records a Notice of Contest of Lien without the use of counsel.  I do not suggest this for a couple of reasons.  First, you want to ensure this is done right and, second, there may be other strategic decisions that may be better implemented based on the circumstances of the dispute.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

QUICK NOTE: NOTICE OF CONTEST OF CLAIM AGAINST PAYMENT BOND

imagesOn private jobs where the general contractor has an unconditional payment bond, subcontractors, sub-subcontractors and suppliers need to serve a notice of nonpayment to preserve payment bond rights.

 

Just like an owner can record a Notice of Contest of Lien to shorten a lienor’s statute of limitations to foreclose the lien to 60 days, a general contractor can record a Notice of Contest of Claim Against Payment Bond.  See Fla. Stat. s. 713.23(e).  When a contractor records a Notice of Contest of Claim Against Payment Bond, the contractor is contesting the notice of nonpayment and shortening the claimant’s period to sue on the payment bond to 60 days from the date of service of the notice.  

 

This tool is used less frequently than the Notice of Contest of Lien; however, it can be a very successful tool for a contractor to use when receiving a notice of nonpayment.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

AN AMENDED LIEN DOES NOT DELAY THE 60 DAY WINDOW TO FORECLOSE A LIEN WHEN A NOTICE OF CONTEST OF LIEN IS RECORDED

imagesI previously discussed the value of an owner recording a Notice of Contest of Lien under Florida Statute s. 713.22 to shorten a lienor’s statute of limitations to foreclose a construction lien to 60 days from the date the lien is contested.   For more information on recording a Notice of Contest of Lien please look at this posting and this posting.

 

What happens if after a Notice of Contest of Lien is recorded the lienor amends its construction lien? For instance, say the following sequence occurs:

 

1:  Lien

2:  Notice of Contest of Lien

3: Amended Lien

 

Does an owner need to record another Notice of Contest of Lien for the Amended Lien?  If an owner does, then a lienor could extend its 60 day window to foreclose its lien by simply recording an amended lien.

 

This exact scenario was addressed long ago by the Florida Supreme Court in Jack Stilson & Co. v. Caloosa Bayview Corp., 278 So.2d 282 (Fla. 1973) which held that the foreclosure of an amended lien MUST still be brought within the 60 days from the initial Notice of Contest of Lien.  In other words, the recording of an amended lien does NOT toll (or stop) the running of the 60 day window to foreclose the lien when a Notice of Contest of Lien is recorded.

 

Therefore, if you are an owner, there is certainly a benefit to recording a Notice of Contest of Lien.  Conversely, if you are a contractor, do not think you can delay or escape the 60 day window to foreclose your construction lien if you received a Notice of Contest of Lien by simply amending your lien.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

 

 

 

 

SERVING CONTRACTOR’S FINAL PAYMENT AFFIDAVIT BY CONTRACTORS (OR SUBCONTRACTORS) IN PRIVITY OF CONTRACT WITH PRIVATE OWNER

imagesContractors (or even subcontractors) in privity of contract with a private owner must serve a Contractor’s Final Payment Affidavit within 5 days before foreclosing on the lien. The objective is to swear to the owner the final payment the contractor is seeking and those unpaid lienors working under the contractor.  This is set forth in Florida Statute s. 713.06(3)(d) which provides:

 

 

 

 

 

 

 

(d) When the final payment under a direct contract becomes due the contractor:

1. The contractor shall give to the owner a final payment affidavit stating, if that be the fact, that all lienors under his or her direct contract who have timely served a notice to owner on the owner and the contractor have been paid in full or, if the fact be otherwise, showing the name of each such lienor who has not been paid in full and the amount due or to become due each for labor, services, or materials furnished. The affidavit must be in substantially the following form:

CONTRACTOR’S FINAL PAYMENT AFFIDAVIT

State of Florida

County of _______

Before me, the undersigned authority, personally appeared (name of affiant) , who, after being first duly sworn, deposes and says of his or her personal knowledge the following:

1. He or she is the (title of affiant) , of (name of contractor’s business) , which does business in the State of Florida, hereinafter referred to as the “Contractor.”

2. Contractor, pursuant to a contract with (name of owner) , hereinafter referred to as the “Owner,” has furnished or caused to be furnished labor, materials, and services for the construction of certain improvements to real property as more particularly set forth in said contract.

3. This affidavit is executed by the Contractor in accordance with section 713.06 of the Florida Statutes for the purposes of obtaining final payment from the Owner in the amount of $___.

4. All work to be performed under the contract has been fully completed, and all lienors under the direct contract have been paid in full, except the following listed lienors:

NAME OF LIENOR  _______AMOUNT DUE

Signed, sealed, and delivered this ____ day of ____, ____.

[Add signature and notary seal] 

 

The contractor shall have no lien or right of action against the owner for labor, services, or materials furnished under the direct contract while in default for not giving the owner the affidavit; however, the negligent inclusion or omission of any information in the affidavit which has not prejudiced the owner does not constitute a default that operates to defeat an otherwise valid lien. The contractor shall execute the affidavit and deliver it to the owner at least 5 days before instituting an action as a prerequisite to the institution of any action to enforce his or her lien under this chapter, even if the final payment has not become due because the contract is terminated for a reason other than completion and regardless of whether the contractor has any lienors working under him or her or not.

 

 

Not timely serving the Contractor’s Final Payment Affidavit 5 days before commencing the construction lien foreclosure action has the unkind affect of invalidating the contractor’s construction lien.  See Timbercraft Enterprises v. Adams, 563 So.2d 1090 (Fla. 4th DCA 1990) (contractor hired to clear land lost its construction lien by failing to timely serve Contractor’s Final Payment Affidavit); Sunair Development Corp. v. Gay, 509 So.2d 1361 (Fla. 2d DCA 1987) (contractor hired to perform painting and carpentry lost construction lien by failing to timely serve Contractor’s Final Payment Affidavit); Bishop Signs, Inc. v. Magee, 494 So.2d 532 (Fla. 4th DCA 1986) (sign contractor lost its construction lien by failing to serve Contractor’s Final Payment Affidavit).

  

If a contractor fails to serve the Contractor’s Final Payment Affidavit before filing its lien foreclosure action, it needs to (a) promptly serve the Affidavit and file an amended complaint within the applicable statutory limitations period, (b) argue that its noncompliance should be excused, or (c) argue that the owner waived the right to invalidate the contractor’s lien through the contractor’s failure to serve a Contractor’s Final Payment Affidavit.

 

A. Serving Affidavit and Amending Complaint within Statutory Limitations Period

 

The Florida Supreme Court in Holding Electric, Inc. v. Roberts, 530 So.2d 301 (Fla. 1988) held that if a contractor fails to timely serve a Contractor’s Final Payment Affidavit before initiating a lien foreclosure lawsuit, the contractor can remedy this noncompliance by serving the affidavit and amending its complaint within the statutory limitations periodSee Holding Electric, 530 So.2d at 302 (“[A]n amended complaint may be filed to show delivery of the contractor’s affidavit, provided the statute of limitations has not run prior to the filing of the amended complaint.”).

 

B. Noncompliance should be Excused

 

In Coquina, Ltd. V. Nicholson Cabinet Co., 509 So.2d 1344 (Fla. 1st DCA 1984), noncompliance with the timely service of the Contractor’s Final Payment Affidavit was excused when the owner contested the lien by recording a Notice of Contest of Lien that shortened the statutory limitations period to foreclose the lien to 60 days and the contractor served the Affidavit 3 days (instead of 5 days) before filing suit.  Notwithstanding, the Fourth District in Pierson D. Construction, Inc. v. Yudell, 863 So.2d 413 (Fla. 4th DCA 2003) still held that the Contractor’s Final Payment Affidavit needed to be served within the applicable statutory limitations period (even if it was not served within 5 days before filing the lawsuit). In other words, not serving it at all could be fatal to the contractor’s lien foreclosure action.

 

Also, the Fourth District in Bishop Signs held, “[t]he applicable concern should be whether it is the type of contract which, by its nature, does not entail the services of subcontractors or the furnishing of labor or material by others.”  Bishop Signs, 494 So.2d at 534. Hence, if the contractor failed to serve the Contractor’s Final Payment Affidavit, it may want to argue that its noncompliance is excused because the type of project it was hired to perform does not entail the services of suppliers or subcontractors.  Though, on most projects, this is a difficult argument to realistically make!

 

C. Owner Waived the Right to Argue Noncompliance

 

In Rivera v. Hammer Head Constr. & Development Corp., 14 So.3d 1190 (Fla. 5th DCA 2009), the contractor failed to serve the Contractor’s Final Payment Affidavit.  The contractor’s complaint pled that all conditions precedent to bringing the action had occurred, had been performed, or were waived.  In response to this allegation, the owner pled is was “without knowledge” as to whether this allegation was true.  The owner, however, did not plead that this was not true because the contractor failed to timely serve a Contractor’s Final Payment Affidavit.  As a result, when the owner raised this issue at trial to invalidate the contractor’s lien, the court held that the owner waived its right to raise this argument because the owner never pled the contractor’s non-performance with any particularity.

 

In conclusion, it is always good practice to timely serve the Contractor’s Final Payment Affidavit within 5 days before filing suit, even if the statutory limitations period is shortened through a Notice of Contest of Lien (or even a lawsuit to show cause).  But, if the Affidavit is not timely served, there are arguments a contractor can raise under the law to try to defeat an owner’s efforts to invalidate the lien due to this noncompliance. 

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.