THINK TWICE BEFORE HEDGING A POSITION OR DEFENSE ON A SPECULATIVE EVENT OR OCCURRENCE

Sometimes, hedging a position on a potential occurrence is not prudent.  Stated differently, hedging a position on a contingent event is not the right course of action.  The reason being is that a potential occurrence or contingent event is SPECULATIVE.   The occurrence or event may not take place and, even if it does take place, the impact is unknown.

An example of hedging a defense on such a potential occurrence or contingent event can be found in a construction dispute involving a federal project out of the Eastern District of Virginia,  U.S. f/u/b/o Champco, Inc. v. Arch Insurance Co., 2020 WL 1644565 (E.D.Va. 2020). In this case, the prime contractor hired a subcontractor to perform electrical work, under one subcontract, and install a security system, under a separate subcontract.  The subcontractor claimed it was owed money under the two subcontracts and instituted a lawsuit against the prime contractor’s Miller Act payment bond.  The prime contractor had issued the subcontractor an approximate $71,000 back-charge for delays.  While the subcontractor did not accept the back-charge, it moved for summary judgment claiming that the liability for the back-charge can be resolved at trial as there is still over $300,000 in contract balance that should be paid to it.  The prime contractor countered that the delays caused by the subcontractor could be greater than $71,000 based on a negative evaluation in the Contractor Performance Assessment Reporting System (“CPARS”).   A negative CPARS rating by the federal government due to the delays caused by the subcontractor would result in a (potential) loss of business with the federal government (i.e., lost profit) to the prime contractor.   The main problem for the prime contractor:  a negative CPARs rating was entirely speculative as there had not been a negative CPARs rating and, even if there was, the impact a negative rating would have on the prime contractor’s future business with the federal government was unknown.   To this point, the district court stated:

In this case, [prime contractor’s] claim for damages is wholly speculative.  [Prime contractor] has not produced any evidence that its stated condition precedent—a negative CPARS rating—will actually occur and will have a negative impact on its future federal contracting endeavors. Specifically, [prime contractor] has not identified any facts that indicate that it will be subject to a negative CPARS rating or any indication of the Navy’s dissatisfaction with its work as the prime contractor on the Project… Further, a CPARS rating is only one aspect taken into consideration when federal contracts are awarded.  In sum, there is no evidence of the following: (1) a negative CPARS rating issued to [prime contractor]; (2) [prime contractor’s] hypothetical negative rating will be the result of the delay [prime contractor] alleges was caused by [subcontractor]; or (3) [prime contractor’s] hypothetical negative CPARS rating will result in future lost profits.

U.S. f/u/b/o Champco, Inc., supra, at *2 (internal citation omitted).

The prime contractor hedged its defense on the potentiality that it would receive a negative CPARs rating and, if it did, it would lose business with the federal government.  Based on this, the prime contractor decided to withhold more than $300,000 in contract balance over and above the $71,000 in delay damages it could prove.  The district court saw right through this argument by finding it wholly speculative and granting summary judgment in favor of the subcontractor for the subcontract balance over and above the $71,000 that the prime contractor did not have an objective basis to withhold.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

A LANDLORD’S REFUSAL TO TIMELY PERFORM NEEDED REPAIRS / MAINTENANCE ITEMS

imagesWhat happens if the landlord refuses to timely repair defects or perform necessary maintenance items that it is otherwise responsible to perform per the lease? What happens if the landlord makes rental space untenantable? The case of Katz Deli of Aventura, Inc. v. Waterways Plaza, LLC, 38 Fla. L. Weekly D2511b (Fla. 3d DCA 2013), illustrates the issue of “constructive eviction” and a tenant’s recourse against its landlord including its recovery of lost profits when a landlord does not timely implement needed repairs that impacts a tenant’s business.

 

In this case, a successful deli in Pembroke Pines opened a new location in a shopping plaza in Aventura. After a couple of years of growing revenue, the deli leased larger space within the same Aventura plaza. The lease for the larger space was for five years, with 3% annual rent increases, and with three lease renewal options for five-year terms. Of importance to this case, the landlord was required to make all of the required repairs to the shopping plaza’s structure and roof.

 

After the execution of the lease, the shopping plaza was purchased by the defendant-landlord (which assumed the deli’s existing lease). The new landlord learned exercising its due diligence of inspecting the plaza’s condition prior to purchase that the roof needed to be replaced (re-roofed). Yet, even though it purchased the plaza, it did not timely replace the roof. As a result, leaks started at the deli and became progressively worse resulting in mold and a musty odor in the deli. Naturally, this condition caused the deli to lose business and customers and reached the point where the deli could not continue to operate as a restaurant. Then, suspiciously, after the deli vacated the space, the landlord decided to re-roof the space and found new tenants that leased the space at a much higher rental rate.  The deli sued the landlord for breach of lease (breach of contract) and constructive eviction.

 

The deli argued that the landlord constructively evicted it in order to capitalize on substantially higher rental rates because the agreed-upon rental rate in the lease that the deli entered into with the former landlord (and that the defendant assumed when it purchased the plaza) was well below market rate.

 

At a bench trial, the deli argued that its damages consisted of lost profits. It utilized an accounting expert to prove lost profits. The landlord contended that lost profits was not the proper damages methodology and the deli should have proven its damages by analyzing the market value of the deli since the deli was destroyed. The reason the landlord argued this is because the deli put on no evidence as to these damages (meaning, if this was the proper methodology, the deli would be entitled to no damages because it failed to put on any evidence of these damages). The trial court found that the deli was entitled to lost profits but only awarded lost profits through the end of the initial lease term, and not the three five year lease renewal options.

 

On Appeal, the Third District Court of Appeal maintained:

 

A constructive eviction constitutes a breach of the covenant of quiet enjoyment. Furthermore, Waterways’ [landlord] grossly negligent failure to repair the roof as required by the lease was a breach of its contract. In an action for breach of contract, the goal is to place the injured party in the position it would have been in had the other party not breached the contract so as to give the aggrieved party the benefit of its bargain. However, a successful plaintiff is not entitled to be placed, because of that breach, in a position better than that which he would have occupied had the contract been performed. The injured party may only recover those damages that naturally flow from the breach and can reasonably be said to have been contemplated by the parties at the time that the contract was made. It is not necessary that the parties have contemplated the exact injury that occurred as long as the actual consequences could have reasonably been expected to flow from the breach.”

Waterways Plaza, supra (internal citations and quotations omitted).

 

When dealing with the issue of a landlord constructively evicting its tenant, there are cases that hold that the measure of damages is the market value of the business as of the date of loss when the business is completely destroyed. This is why the landlord argued that this should have been the damages methodology employed by the deli. “However, where, as here, a business [the deli] continues after suffering from an act of negligence the business is entitled to recover the lost profits attributable to defendant’s [landlord] negligent act, but cannot recover both lost profits, and the market value of the business.” Waterways Plaza, supra (internal quotations omitted).

 

The deli was not completely destroyed when the leaks started. Rather, the leaks progressed over a period of time until the space was untenantable. Largely for these reasons, there was no bright line test as to when the deli was completely destroyed. As the Third District explained: “Awarding market value for a business that has been slowly reduced to nothing due to a defendant’s breach, thereby leaving the plaintiff without an adequate recovery, would be completely inequitable, and is not the law in Florida.” Waterways Plaza, supra.

 

Since lost profits was the proper damages methodology, the Third District next analyzed whether the deli sufficiently proved such damages during the trial.

 

Lost profits are recoverable regardless of how well established a business is so long as there is some ‘yardstick’ by which prospective profits can be measured.
***
A business can recover lost prospective profits regardless of whether it is established or has any ‘track record.’ The party must prove that 1) the defendant’s action caused the damage and 2) there is some standard by which the amount of damages may be adequately determined.
***
Any ‘yardstick’ used to show the amount of profits must be reasonable, and the loss of the profits as a result of the [defendant’s conduct] must be reasonably certain. Lost profits must be established with a reasonable degree of certainty and must be a natural consequence of the wrong. The projected profits cannot be mere speculation or conjecture, but the inability to prove a precise damages amount will not prevent a plaintiff from recovering so long as it is clear that some loss resulting from the defendant’s actions is certain.”

Waterways Plaza, supra.

 

The deli was able to establish a yardstick because it had another location in Pembroke Pines, had success at its former smaller space within the same shopping plaza, and had limited success during the short time it was in the larger space prior to the leaks. Thus, it was able to demonstrate a history of sales that enabled its expert to establish sale projections and projected profit.

 

Even though lost profits was the proper damages methodology, the deli wanted lost profits that extended through all lease renewals. The deli argued it clearly would have renewed the lease based on the success at that location and plaza prior to the leaks, because its rent was well below market rate, and because the successor tenants leasing the same space after the re-roof were still leasing the space close to ten years after the deli vacated the space. Despite this evidence, the Third District held that this was a question of fact to be determined by the trier of fact, and because the fact finder was the judge, the judge’s fact finding will be presumed correct on appeal unless clearly erroneous. Since the trial judge found that lost profits extending beyond the original five year lease term was speculative, the Third District affirmed the court’s fact finding because it was not clearly erroneous.

 

Notably, the deli also tried to foreclose an equitable lien and recorded a lis pendens against the shopping plaza. The deli’s equitable lien theory was based on the following language in the lease: “Tenant shall look solely and only to the Landlord’s interest in the Plaza in the event of any default or breach.” Waterways Plaza, supra. However, the lis pendens was discharged and the equitable lien claim was dismissed by the trial court. The deli appealed this arguing that the dismissal of the lis pendens to foreclose its equitable lien was error. The Third District affirmed the trial court finding that the language in the lease did not give the tenant an interest in the landlord’s property that would entitle it to an equitable lien and lis pendens.

 

This case illustrates options a tenant has when its rental space becomes untenantable, especially due to the landlord’s failure to timely implement or perform needed repairs / maintenance items. This case further illustrates the importance of knowing and proving a party’s correct damages methodology due to a breach.  Also, considering the factual circumstances in lost profit cases, such as this case, and how a party establishes its lost profits provides future guidance to ensure that these damages are proven with their required reasonable degree of certainty!

 

 

For more information on proving lost profits, please see: https://floridaconstru.wpengine.com/proving-lost-profit-damages-with-a-reasonable-degree-of-certainty/

 

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

 

PROVING LOST PROFIT DAMAGES WITH A REASONABLE DEGREE OF CERTAINTY

images-1Lost profit damages are challenging damages to prove, but are an important form of consequential damages that parties seek based on the dynamics of the case. These damages must be proven with a reasonable degree of certainty. The recent Southern District of Florida opinion, Topp Paper Co., LLC v. ETI Converting Equipment, 2013 WL 5446341 (S.D.Fla. 2013), explained:

 

Under Florida law, lost profits must be proven with a reasonable degree of certainty before the loss is recoverable. Courts have construed this standard as requiring that the mind of a prudent or impartial person be satisfied that the damages are not the result of speculation or conjecture. In unproven businesses such as Topp’s [plaintiff], Florida courts have allowed damages where the plaintiff proves that (1) the defendant’s action caused the damage and (2) there is some standard [yardstick] by which the amount of damages may be adequately determined.” Id. at *7 (internal citations and quotations omitted).

 

The first step is the causation requirement, i.e., that the defendant’s conduct caused the lost profit damages that the plaintiff seeks.

 

The second step is the lost profit methodology demonstrating the plaintiff’s lost profit damages with a reasonable degree of certainty and without speculation. Oftentimes parties retain experts to prove these damages based on the yardstick or standard in which the lost profit damages are determined. However, in Topp Paper, the Southern District maintained that both steps “may be satisfied without resort to expert testimony.” Topp Paper, supra, at *8.  In this case, the plaintiff, a new business, planned to show lost profits without an expert by laying the foundation for cancelled contracts with its clients that were solely caused by the defendant’s actions. The plaintiff’s position was that but for defendant’s actions, it would have been able to satisfy the contracts with its actual clients and, because it was not able to, it lost the profit associated with those contracts.

 

On the other hand, the Southern District would not allow the plaintiff to prove its lost profit damages through income projections by comparing projected income with actual income to assess lost profits. The reason is that establishing lost profit damages through projections would be purely speculative, especially considering the plaintiff’s business was a new business without a history of profits.

 

In Topp Paper, the plaintiff could be in a position to establish lost profits because it actually had contracts with clients that had to be cancelled due to the defendant’s alleged actions. This was vital because the plaintiff could establish lost profits without the need to retain an expert. However, what if the plaintiff, as a new business, did not actually have cancelled contracts? It would not be able to prove damages through income or profit projections. In this scenario, the plaintiff would need to establish some yardstick to prove its damages with a reasonable degree of certainly. One yardstick could be the plaintiff’s past business and profit history. A plaintiff’s accountant or financial officer could assist in this methodology / calculation (although, if possible, it helps to have this supported by an expert). However, as a new business, the plaintiff did not have a business history. The other way would be to find a comparable business with a comparable business model as the yardstick to establish lost profits. This should require expert testimony and it will be important to work with the expert and cross-examine the expert to flesh out any speculative portion of the yardstick.

 

The bottom line is that lost profit damages are challenging and require a game plan that will be used to support (1) causation–that the defendant’s action caused these damages and (2) the standard or yardstick that will be utilized to support lost profit damages. A new business will likely have a different game plan than an established business unless there is documentary evidence (such as in Topp Paper) that the business had actual clients that would have been serviced but for the defendant’s actions. Also, knowing that income projections or pro forma profit and loss statements will be deemed speculative, getting an expert involved sooner than later is important to assist with establishing the yardstick or methodology that will be used to prove lost profits with a reasonable degree of certainty.

 

For more information on lost profit damages, please see https://floridaconstru.wpengine.com/the-difference-between-lost-profit-and-loss-of-use-damages/

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

THE DIFFERENCE BETWEEN LOST PROFIT AND LOSS OF USE DAMAGES

ProfitSharingLost profits are a type of damages that are sometimes thrown around in a litigation.  However, these damages are very difficult to establish and prove and they really require expert testimony.  If the theory to recover lost profits is speculative, or the way the lost profits is measured is speculative, they will not be recoverable.  (Typically, lost profits require a history of profits to measure against and/or establishing the profitability of another business using a substantially similar business model for comparative purposes).  Lost profit damages have a difficult burden of proof in order to avoid the argument that they are speculative in nature.

 

Loss of use is another type of damages that is often confused with lost profit damages. Loss of use damages is generally the rental value of property / fair market value due to the loss of use of that property. See B&B Tree Service, Inc. v. Tampa Crane & Body, Inc., 38 Fla. L. Weekly, D970a (Fla. 2d DCA 2013) citing MD. Cas. Co. v. Fla. Produce Distribs., Inc., 498 So.2d 1383 (Fla. 5th DCA 1986) and Meakin v. Dreier, 209 So.2d 252 (Fla. 2d DCA 1968).  Hypothetically speaking, this type of damage can come into play if an owner is trying to recoup the rental value of units / fair market value of units that are out of service due to a defect, i.e., water intrusion problem.

 

There is a better argument for an owner under Florida caselaw to testify as to loss of use damages than lost profits, although with both types of damages, a qualified expert is preferential. “An owner is qualified to testify to the value of his property based on a presumed familiarity with the characteristics of the property, knowledge or acquaintance with its uses and purposes, and experience dealing with it….An owner must be shown to have knowledge regarding the property and its value sufficient to qualify him.” B&B Tree Service quoting Craig v. Craig, 982 So.2d, 724, 729 (Fla. 1st DCA 1993) (internal quotations omitted). The key is the owner’s familiarity with the property and value to support his opinion testimony regarding loss of use damages.

 

Understanding the differences between lost profit damages and loss of use damages, as well as the ways to prove such damages, is important if these are damages a party is looking to recover. Not understanding the burdens of proof for these types of damages can be fatal to recovery or can lead a party to an unrealistic method of thinking during the course of a case and prevent the party from entertaining reasonable settlement offers.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.