SPEARIN DOCTRINE CAN APPLY IN DESIGN-BUILD CONTEXT

The Spearin doctrine is a doctrine in the construction industry that broadly means the owner impliedly warrants the constructability of the plans and specifications given to the contractor. This implied warranty attaches to a design specification, but not a performance specification. A question arises as to whether the Spearin doctrine can apply in the design-build context where the contractor is responsible for both the design and construction.  It can, as discussed in the case below.

In Balfour Beatty Construction, LLC v. Administrator of the General Services Administration, 2025 WL 798865 (Fed. Cir. 2025), a design-build contractor appealed a decision from the Civilian Board of Contract Appeals (Board) claiming it was entitled to recover for design errors in the government’s bridging documents. In other words, the contractor claimed there was a design defect in the government’s bridging documents and, pursuant to the Spearin doctrine, the government should be liable for the contractor’s increased costs.

Often, in a design-build solicitation, there are bridging documents which are basically conceptually design documents as to what the government is looking for with the objective for the design-build contractor to complete the design. There is oftentimes a disclaimer reflecting the preliminary or conceptual nature of the bridging documents and that they are not intended to describe the full scope of the design or the work.

Here, the design-build contractor submitted a claim for increased costs due to design errors based in the bridging documents.  One issue dealt with claimed design defects with the mat slab foundation in the bridging documents. The contractor argued it needed to “redesign and depart from the bridging documents to accommodate a thicker mat slab, which was required to handle the loads of the equipment and bridging columns.” Balfour Beatty, supra, at *2.

Regarding the Spearin doctrine:

In United States v. Spearin, the Supreme Court held that “if the contractor is bound to build according to plans and specifications prepared by the owner, the contractor will not be responsible for the consequences of defects in the plans and specifications.” We have since clarified that this implied warranty attaches in contracts that contain design specifications, which “explicitly state how the contract is to be performed and permit no deviations.” But if the contract contains a performance specification, which specifies the result to be obtained but leaves the contractor free to determine how to achieve those results, the implied warranty does not attach.

In a design-build bridging project delivery method, the government provides a partial design with the expectation that the contractor will complete the design and build the project. The Board analyzed the provisions of the contract and“consider[ed] to what extent a thirty-percent design … was design or performance.” The Board determined that the bridging documents did not contain a warranty for the design of the mat slab at a particular thickness. The Board noted that, in addition to the contract drawing that directed the contractor to match the existing foundation thickness of 18 inches, [the government] provided calculations from [government] consultants that called for a 24-inch foundation. TheBoard concluded that because these documents “raised a question about the mat slab thickness that should have caused [the contractor] to raise the issue before contract award,” [the contractor] was not entitled to recover costs related to designing the thicker mat slab. We disagree.

The contract drawing indicated that [the contractor] should “match existing building foundations,” which were 18 inches thick. We determine the language in the drawing is sufficiently definite to constitute a design specification, and the Board erred in construing this as a performance specification. We conclude that there was an implied warranty with respect to the mat slab thickness. Further, even if there were a conflict between the drawing and the calculations, the mat slab [the contractor] ended up having to build was between 43 and 53 inches thick—almost double what the calculations required.

Balfour Beatty, supra, at *2 (internal citations omitted).

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

SUBSEQUENT PURCHASER CAN ASSERT CLAIMS FOR CONSTRUCTION DEFECTS

Can a subsequent purchaser pursue construction defect claims relating to the original construction of the property?  This was the threshold issue on a motion for summary judgment by a drywall manufacturer against a subsequent purchaser of a home in Karpel v. Knauf Gips KG, 2022 WL 4366946 (S.D. Fla. 2022).  This matter deals with the defective Chinese drywall that was installed in homes years ago.  The plaintiffs, which were subsequent purchasers of a home, sued the manufacturer of the defective drywall for various theories including negligence, negligence per se, strict liability, breach of express and/or implied warranty, private nuisance, unjust enrichment, and Florida’s Deceptive and Unfair Trade Practices Act.

The trial court noted, from the onset, that Florida does NOT have a subsequent purchaser rule that prohibits subsequent purchasers from asserting construction defect claims. With this consideration in mind, the trial court went through the claims the plaintiff, as a subsequent purchaser, asserted against the manufacturer to determine whether they were viable claims as a matter of law.

Negligence Claim

The trial court found that a subsequent purchaser could sue in negligence.  “Florida courts have long allowed subsequent purchasers to sue for negligence including in construction defect litigation.”  Karpel, supra, at *2.

Negligence Per Se and Strict Liability Claims

The trial court held that the plaintiff’s negligence per se and strict liability claims were duplicative. Both could not stand; for this reason, the court entered summary judgment as to the duplicative negligence per se claim. “Strict liability means negligence as a matter of law or negligence per se, the effect of which is to remove the burden from the user of proving specific acts of negligence.Karpel, supra, at *3 (quotation and citation omitted).

A subsequent purchaser could pursue a strict liability claim against a manufacturer.  “[A] manufacturer is strictly liable in tort when an article he places on the market, knowing that it is to be used without inspection for defects, proves to have a defect that causes injury to a human being.”  Karpel, supra, at *4 (quotation and citation omitted).

Even Section 402A of the Second Restatement of Torts, adopted by Florida’s Supreme Court, provides: “(1) One who sells any product in a defective condition unreasonably dangerous to the user or consumer or to his property is subject to liability for physical harm caused to the ultimate user or consumer, or to his property, if (a) the seller is engaged in the business of selling such product, and (b) it is expected to and does reach the user or consumer without substantial change in the condition in which it is sold.” Karpel, supra, at *4.

There are, however, limits on strict liability.

First, Florida disallows recovery in tort where plaintiffs only claim economic losses such as ‘damages for inadequate value, costs of repair, and replacement of the defective product, or consequent loss of profits—without any claim of personal injury or damage to other property.Karpel, supra, at *4 (citation omitted).

Second, Florida courts will disallow recovery for strict liability where the purchaser was subject to the common law doctrine of caveat emptor.”  Karpel, supra, at *4.

Thus, a subsequent purchaser’s strict liability claim could be pursued against a manufacturer provided such damages are not barred by the economic loss rule or the doctrine of caveat emptor (which applies to commercial property and property purchased at judicial auction sales).  Karpel, supra, at *4.

Breach of Implied Warranty

The trial court found that a subsequent purchaser could NOT sue a manufacturer for breach of implied warranty.  “[I]t is abundantly clear that in cases like these, where no contractual relationship between a subsequent purchaser and a manufacturer exists, the former’s recourse is a claim for strict liability.Karpel, supra, at *4.

Breach of Express Warranty

While a contractual relationship is typically required for breach of express warranty, this requirement is relaxed if the express warranty is intended to benefit subsequent purchasers.  “A manufacturer’s liability for breach of an express warranty derives from, and is measured by, the terms of that warranty.”  Karpel, supra, at *4 (quotations and citation omitted).  However, in this case, plaintiff’s breach of express warranty claim failed because the plaintiff never introduced any express warranty into the record.

Private Nuisance

The trial court held that the subsequent purchaser could NOT pursue a private nuisance claim against the manufacturer.   To sustain a private nuisance claim, the plaintiff must prove that the defendant’s maintenance of the nuisance was the proximate cause of the plaintiff’s damages.  Karpel, supra, at *8.  “The Plaintiffs’ ownership and current control over the drywall conclusively forecloses them from arguing that the Defendants actively “maintain” the ‘nuisance’ they complain of.”  Id.

Unjust Enrichment

The trial court held that the subsequent purchaser could NOT pursue an unjust enrichment claim against the manufacturer.  An unjust enrichment claim requires the plaintiff to prove that the plaintiff conferred a direct benefit on the defendant. “The Plaintiffs conferred no direct benefit on the Defendant.” Karpel, supra, at *8 (finding that plaintiffs, as subsequent purchasers, obtained their homes from previous owners so the plaintiffs conferred no direct financial benefit on the manufacturer).

Florida’s Deceptive and Unfair Trade Practices Act (FDUTPA)

The trial court found that a subsequent purchaser could theortetically pursue a FDUTPA claim. “Because the law is clear that a plaintiff need not have actually relied on the purported deceptive or unfair practice, the Court’s analysis need not go further….The Plaintiffs’ status as subsequent purchasers does not foreclose them from arguing that the Defendants’ practices violated FDUTPA.”  Karpel, supra, at *9.

However, the trial court noted that actual damages under FDUTPA may implicate the economic loss rule because actual damages under the statute “are the difference in the market value of the product or service in the condition in which it was delivered and its market value in the condition in which it should have been delivered according to the contract of the parties.”  Karpel, supra, at *9 (quotation and citation omitted). For this reason, the court ordered the plaintiff and defendant to submit supplemental briefing because if the economic loss rule is implicated, the FDUTPA claim will fail (due to the same limitations relating to the strict liability claim).

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

EXPRESS WARRANTY TRUMPING SPEARIN’S IMPLIED WARRANTY

Be mindful of that express warranty provision in your contract.  It could result in an outcome that you did not consider or factor when submitting your proposal or agreeing to your contract amount.

An express warranty could have the effect of eviscerating the argument that you performed your scope of work pursuant to the plans and specifications.   In other words, the applicability of the Spearin doctrine could be rendered moot based on express warranty language in your contract that is fully within your control because you do not have to agree to that language.

Under the Spearin doctrine:

 [W]hen a ‘contractor is bound to build according to plans and specifications prepared by the owner, the contractor will not be responsible for the consequences of defects in the plans and specification.’ Spearin and its progeny set forth a default rule of fundamental fairness that when a general contractor requires a subcontractor to follow certain plans and specifications, the general contractor impliedly warrants that those plans and specifications are ‘free from design defects.’  Put simply, Spearin protects subcontractors from liability for simply following the general contractor’s direction and requirements.

However, the implied warranty set forth in Spearin and its progeny may be overcome by express agreement.   Where a general contractor and subcontractor expressly agree to allocate the risk of a defective product to the subcontractor, that express agreement must prevail over Spearin’s implied warranty

Lighting Retrofit International, LLC v. Consellation NewEnergy, Inc., 2022 WL 541156 (D. Md. 2022) (internal citations omitted).

Does this underlined language above mean that an express warranty provision in a contract can trump the Spearin doctrine’s implied warranty of building according to the plans and specifications?  According to this decision in Lighting Retrofit International, the answer is a resounding yes!

This case involved energy savings construction improvements to a federal prison in Florida, although the dispute was decided under Maryland law (likely due to a choice of law and venue provision in a subcontract).  A subcontract between the prime contractor and a subcontractor was predicated on LED retrofit kits from a specific manufacturer for certain exterior lights.  There was no other manufacturer that offered such retro kits on the market.

The subcontract contained a very detailed express warranty provision:

 6.8 Warranties. Subcontractor warrants that (a) all services will be provided by qualified, competent and professional persons in a timely, good and workmanlike manner and with a degree of skill and care in conformity with industry standards, (b) all equipment will be free from defects and installed in accordance with manufacturer’s specifications, and (c) all services and equipment shall be in compliance with all applicable laws, licenses, and permits. Subcontractor will obtain vendor/ manufacturer/supplier warranties and pass through all such warranties to both Constellation [prime contractor] and Constellation’s Customers. Subcontractor shall, if available, with the prior written approval of Constellation, obtain extended warranties, and pass through all such extended warranties to both Constellation and Constellation’s Customers. The Subcontractor shall, at its sole expense interface, and act as liaison with Subcontractor-purchased materials manufacturers, vendors, and suppliers to resolve problems and pursue warranty claims on behalf of Constellation and Constellation’s Customers. In the event a manufacturer, vendor, or supplier of such materials ceases operations or is otherwise unable to meet its warranty obligations to Constellation or Constellation’s Customers, Subcontractor agrees to provide or secure, at its sole expense, for Constellation and Constellation’s Customers, all such warranties including but not limited to any required spare parts.

The warranties set forth herein shall continue for a period of one (1) year after the date of Constellation’s final acceptance of the work or Customer’s beneficial use, whichever is later, unless a longer period is set forth in the Contract DocumentsUnless otherwise provided on the Scope of Work, if the services and materials provided by Subcontractor hereunder do not conform to the warranties included herein, then Subcontractor will (at its sole cost and expense) do any of the following upon Constellation’s request: (a) re-perform the services, or repair or replace the equipment, in a satisfactory manner that conforms to the terms of this Subcontract, (b) pay Constellation any money damages that Constellation owes as a result of nonconformance and refund the portion of the cost hereunder which is attributable to such nonconformance, (c) if Constellation chooses to correct the breach by re-performing the services or repairing or replacing the equipment, (by itself or through another subcontractor), pay Constellation any expenses Constellation incurs itself or pays a third party. This warranty shall not in any way limit any standard warranties provided by Subcontractor to its customers generally.

The LED retrofit kits failed miserably resulting in a dispute between the prime contractor and subcontractor.  The subcontractor was not paid and filed a lawsuit.  The prime contractor had to hire another subcontractor to ultimately remediate the failure and countersued.

The subcontractor argued under the Spearin doctrine, i.e., that the prime contractor impliedly warranted the LED retrofit kits which the subcontractor furnished for the project.

The issue was whether the express warranty provision above should supersede Spearin’s implied warranty.  In reviewing this issue, the Court noted cases in jurisdictions other than Maryland where an express warranty trumped Spearin’s implied warranty; however, there was a case from Missouri where Spearin’s implied warranty trumped an express warranty  due to a circumstance outside the party’s control.  See Lighting Retrofit International, supra, at *6.

Yet, even giving the subcontractor the benefit of the doubt, the Court noted this was NOT an issue beyond the subcontractor’s control.

While the fact the retrofit kids failed was beyond the subcontractor’s control, the subcontractor was free to negotiate the express warranty provision in its subcontract – the express warranty provision was within its control: “[E]ven assuming [the prime contractor] forced [the subcontractor] to use that particular product, [the subcontractor] freely and willingly agreed to the unequivocal warranty provisions in the Subcontract – a conscious choice that was, undoubtedly, within [the subcontractor’s] control.”  Lighting Retrofit International, supra, at *6.   “Therefore, an implied warranty that exists to prevent a general contractor from unfairly taking advantage of a subcontractor for merely following the general contractor’s directions must yield where a sophisticated subcontractor expressly agrees to shoulder the risk.” Id.

Is this a harsh outcome?   You betcha!   And it’s a harsh outcome form an express warranty provision that contains language that exists in some fashion in many contracts.  This outcome goes to the point that it all starts with your contract and what you are agreeing to on the frontend.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.