UNLICENSED CONTRACTING AND FLORIDA STATUTE s. 489.128

Florida Statute s. 489.128 is a statute that provides a remedy against unlicensed contracting.  However, keep in mind that this argument—the unlicensed contractor argument—is a technical statutory argument. In other words, it’s not so much of a fact-based merits argument, but an argument that’s solely based on the technicality of the statute. This, by no means, is not a recommendation that the argument should not be raised. In instances, it absolutely should be and could have legitimate traction. However, when deciding whether to or how to pursue a dispute, including settlement, you want to keep in mind whether this is an argument you want to bank your outcome on because there are always costs (attorney’s fees, court costs, etc.) that should get factored into any business decision regarding a dispute.

A recent decision out of Florida’s Fourth District Court of Appeal discussed the application of Florida Statute s. 489.128:

Section 489.128, Florida Statutes…provides a limited remedy for parties who have contracted with unlicensed contractors: “As a matter of public policy, contracts entered into . . . by an unlicensed contractor shall be unenforceable in law or in equity by the unlicensed contractor.” § 489.128(1), Fla. Stat. This remedy applies not only to individual contractors, but also to entities: “A business organization is unlicensed if the business organization does not have a primary or secondary qualifying agent in accordance with this part concerning the scope of the work to be performed under the contract.” § 489.128(1)(a), Fla. Stat. In other words, if a contracting entity does not have at least one agent with an appropriate license, the entity is also considered “unlicensed.”

Chapter 489’s “unenforceable contract” remedy, however, is explicitly restricted to contractor work requiring a state license: “if a state license is not required for the scope of work to be performed under the contract, the individual performing that work is not considered unlicensed.” § 489.128(1)(a), Fla. Stat. (emphasis added). More importantly, section 489.128 contains no provisions permitting local entities to enforce this remedy.

Section 489.127, Florida Statutes (2018), in contrast, provides remedies for contractors who “[e]ngage in the business or act in the capacity of a contractor . . . without being duly registered or certified [as competent.]” § 489.127(1)(f), Fla. Stat. (emphasis added). The remedies are mostly criminal penalties. § 489.127(2)-(6), Fla. Stat. Notably, no language in section 489.127 refers to section 489.128.

Section 489.127 provides a much broader remedy than section 489.128, in that section 489.127 specifically permits local entities to enforce its provisions:

Each county or municipality may, at its option, designate one or more of its code enforcement officers . . . to enforce, as set out in this subsection, the provisions of subsection (1) and s. 489.132(1) against persons who engage in activity for which a county or municipal certificate of competency or [state] license or state certification or registration is required.

489.127(5), Fla. Stat. (emphasis added). Again, it is notable that no language in section 489.127 refers to section 489.128. Importantly, section 489.127 makes clear that the grant of power to local entities is limited to the section 489.127 remedies, not chapter 489 in general.

Thus, chapter 489 provides separate and exclusive remedies against (1) contractors failing to hold state licenses when required, and (2) contractors that are not “registered or certified” when required. Chapter 489 permits counties to enforce remedies against registration and certification violations but not state license violations.

Palm Beach Resurfacing, Inc. v. Floyd, 50 Fla.L.Weekly D194a (Fla. 4th DCA 2024).

In Palm Beach Resurfacing, a homeowner hired a company to perform pool resurfacing work.  A dispute arose and the company recorded a construction lien. The homeowner argued the contractor was not licensed pursuant to a Palm Beach County ordinance and, as a result, the lien and contract should be unenforceable as a matter of law.  The contractor countered that while it was not licensed in Palm Beach County, a state license was NOT required for it to perform pool resurfacing work, which is correct, and thus, Florida Statute s. 489.128 does not apply. The trial court nonetheless granted summary judgment against the contractor for not being licensed in Palm Beach County.

However, based on the analysis above, the Fourth District Court of Appeal reversed: “Having determined the trial court erred in construing statutes and local ordinances and codes in applying the statutory unenforceable remedy, we reserve the grant of summary judgment and direct the trial court to vacate the order granting summary judgment….”  In other words, there is no state license requirement for the contractor to have a state license to perform pool resurfacing work.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

ENFORCEABILITY OF CONTRACT AS A WHOLE TO BE DETERMINED BY ARBITRATOR AND NOT A BASIS TO VACATE ARBITRATION AWARD


Arbitration is a form of dispute resolution that parties elect in their contracts.  With respect to construction contracts, the arbitration provision may provide that the parties will submit their dispute to the American Arbitration Association.  A benefit to arbitration is that the dispute will be decided by an arbitrator or panel of arbitrators that theoretically have expertise in the subject matter of the dispute.  A downside is that there is no great avenue to appeal or vacate an arbitrator’s award (absent very limited circumstances) even if a party believes the arbitrator misapplied the law.

 

An example of this downside can be found in The Village of Dolphin Commerce Center, LLC v. Construction Service Solutions, LLC, 39 Fla. L. Weekly D1065a (Fla. 3d DCA 2014), where an owner hired a contractor to construct a warehouse. At the time of contract, the contractor was not licensed.  The contractor became licensed after the execution of the contract.  The contractor proceeded with construction and, due to a payment dispute, recorded a construction lien.  The contractor also filed a demand for arbitration with the American Arbitration Association pursuant to its contract. The owner answered the demand for arbitration and asserted as a defense that the contract was unenforceable pursuant to Florida Statute s. 489.128 which provides, “As a matter of public policy, contracts entered into…by an unlicensed contractor shall be unenforceable in law or in equity by the unlicensed contractor.”   Section 489.128 further provides that, “[i]f a contract is rendered unenforceable under this section, no lien or bond claim shall exist in favor of the unlicensed contractor….”

 

The owner further filed a lawsuit in circuit court asking the court to declare that that the contractor’s claim of lien was unenforceable since the contractor was unlicensed at the time of contract.  The contractor asserted a counterclaim (although it is uncertain what claims were asserted) and moved to compel arbitration; the circuit court stayed the action and compelled the parties to arbitrate the dispute.

 

During arbitration, the owner never objected to the arbitrator’s jurisdiction to rule on whether the contractor’s lack of license at the time of contract prevented it from enforcing the contract and the construction lien. “The rules of the American Arbitration Association specifically state that any objection to the panel hearing an issue must be submitted with the answering statement or it is determined that the panel will have jurisdiction.”  The Village at Dolphin Commerce Center, supra.

 

The contractor prevailed in the arbitration and moved to enforce the arbitration award in circuit court.  The owner moved to vacate the award based on the unenforceability of the contract and lien under s. 489.128 (because the contractor was not properly licensed at the time of its contract with the owner).  The trial court affirmed the arbitration award and the owner appealed.

 

The issue on appeal was whether the arbitrator had jurisdiction to determine the enforceability of the contract and the lien pursuant to s. 489.128.   The Third District held that it did:

 

“[T]he issue of enforceability was submitted to the panel and neither party objected.  As such, based on the AAA [American Arbitration Association] rules, the panel had jurisdiction to determine the issue.  To ask the trial court to revisit the issue would require the trial court to step into an appellate position.   The Florida Arbitration Statutes do not provide for such.  Pursuant to section 682.13, Florida Statutes, the authority of the trial court to vacate an arbitration award is very narrow.”

The Village at Dolphin Commerce Center, supra.

 

 

The Third District, relying primarily on the United States Supreme Court’s decision in Buckeye Check Cashing, Inc. v. Cardegna, 126 S. Ct. 1204 (2006), as well as other Florida appellate decisions, maintained that when a party is challenging the legality / enforceability of a contract as a whole (versus only the arbitration provision), that determination MUST go to the arbitrator and not the court.  For this reason, the Court held, “Those cases make clear that a trial or appellate court’s view that an arbitration panel wrongly decided the issue of illegality of a contract, and specifically illegality of a contract under section 489.128, is not a basis to vacate an arbitration award.” The Village at Dolphin Commerce Center, supra.

 

 


Now, there are interesting take-aways from this ruling that need to be considered: 

 

    • If a party is arguing that a contract that contains an arbitration provision is unenforceable as a whole (such as being unenforceable because the contractor was not licensed at the time of contract), that determination should go to the arbitrator and not the court.   Yet, even the Third District noted that the Fourth District in Jupiter Medical Center, Inc. v. Visiting Nurse Association of Florida, Inc., 72 So.3d 184 (Fla. 4th DCA 2011), entered a ruling that conflicted with the United States Supreme Court (and, thus, the instant ruling) by stating: “If [a] contract is found to be illegal, a prior arbitration will not prevent the trial court from vacating the award.”  The Village at Dolphin Commerce Center, supra, quoting Jupiter Medical Center, Inc., 72 So.3d at 186.  How should this be reconciled with the instant ruling?  If a party in arbitration under the rules of the American Arbitration Association wants to preserve its argument that the arbitrator does not have jurisdiction to rule on the enforceability of the contract and lien under s. 489.128, it needs to (a) timely object to the arbitrator’s jurisdiction in accordance with the American Arbitration Association’s rules to ensure this argument is not waived and (b) hope that the court agrees with the Fourth District’s ruling in Jupiter Medical Center that a court can vacate an arbitration award if a contract is found to be illegal.  More than likely, however, the court will do exactly what the Third District did in The Village at Dolphin Commerce Center by holding that the arbitrator has the authority to determine the enforceability of a contract when the legality of the contract is be challenged as whole.

 

    • If a party wants to have the ability to appeal a ruling, particularly a ruling that involves a potentially incorrect application of the law, that party should NOT agree to a contract that contains an arbitration provision.  There is no discussion in this case (and the appellate court likely did not know) why the arbitration panel overlooked the fact that the contractor was not properly licensed and/or the reasons it found that s. 489.128 did not apply.  It did appear from the opinion, however, that the contractor was not properly licensed at the time of the contract and that s. 489.128 should have applied.

 

    • Determine whether the party being hired is licensed at the time of contract. Also, if a party is required to be licensed at the time of contract, it should get licensed in order to avoid having the other party to the contract argue that the contract and/or lien is unenforceable.

 

    • Recently, I discussed the Second District Court’s opinion in Snell v. Mott’s Contracting Services, Inc., 39 Fla. L. Weekly D1053a (Fla. 2d DCA), where the Court held that the contractor’s lien was unenforceable because the contractor did not timely enforce the lien in court after receiving a Notice of Contest of Lien.  (See https://floridaconstru.wpengine.com/dont-forget-to-timely-foreclose-the-construciton-lien-in-court/).   There is no discussion in The Village at Dolphin Commerce Center whether the contractor ever moved to foreclose its lien in court. Most likely, it asserted a lien foreclosure action in its counterclaim against the owner in court that was stayed pending the arbitration.  However, if it did not, then there would remain an issue as to how the lien is enforceable if it was not timely foreclosed on in court.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.