HUH? ACTION ON CONSTRUCTION LIEN “RELATES BACK” DESPITE NOTICE OF CONTEST OF LIEN

Not every case law you read makes sense. This sentiment goes to the uncertainty and grey area of certain legal issues.  It is, what you call, “the nature of the beast.”  You will read cases that make you say “HUH?!?” This is why you want to work with construction counsel to discuss procedures and pros / cons relative to construction liens.

An example of a case that makes you say “HUH” can be found in Woolems, Inc. v. Catalina Capstone Creations, Inc., 2023 WL 2777506 (Fla. 3d DCA 2023) dealing with a construction lien foreclosure dispute.

Here, a contractor filed a lawsuit against a subcontractor with a summons to show cause why the subcontractor’s construction lien should not be discharged.  This is a specific complaint filed under Florida Statute s. 713.21(4). This statute requires the lienor to essentially foreclose on its construction lien within 20 days after it was served with a “show cause” summons.  The subcontractor filed its answer and counterclaim but did NOT assert a claim to foreclose its construction lien.

Around the time of subcontractor’s answer and counterclaim, the contractor transferred the subcontractor’s lien to an all-cash lien transfer bond in accordance with Florida Statute s. 713.24. Once the lien transfer bond was recorded, the owner recorded a notice of contest of lien under Florida Statute s. 713.22. The notice of contest of lien shortens the limitations period to foreclose on a lien to 60 days.

The subcontractor did NOT timely foreclose its lien against the lien transfer bond and the general contractor moved to have its all-cash lien transfer bond returned, as it should do. The subcontractor filed its lien foreclosure against the lien transfer bond AFTER the 60-day window expired. The trial court, and affirmed by the appellate court, denied the general contractor’s request to have the lien transfer bond returned and allowed the subcontractor to assert its (dilatory) claim against the lien transfer bond claiming it related back in time to the subcontractor’s initial counterclaim.  HUH?!?

ISSUES GIVING RISE TO THE HUH

Here are the issues with this ruling:

  1. The subcontractor should have foreclosed its construction lien with the 20-day time period from receiving the summons to show cause. The case reflected the subcontractor asserted claims, but not the lien foreclosure claim subject to the summons to show cause. (The appeal did not discuss this point for reasons currently unknown.)
  2. Regardless of (1), the lien was transferred to a bond and a notice of contest of lien was recorded shortening the time period to foreclose the lien (as to the bond) to 60 days. There is case law referencing this procedure. Yet, the subcontractor still did not timely assert its claim against the lien transfer bond.
  3. The trial court applied the relation back doctrine which does nothing but completely water down the statutory purpose of a notice of contest of lien (not to mention the summons to show cause complaint).

RECOMMENDATIONS IN LIGHT OF RULING

In light of this ruling, here are my recommendations:

  1. If you are going to transfer a lien to a lien transfer bond, do it from the get-go. Then, record the notice of contest or pursue the summons to show cause complaint.
  2. If filing the summons to show cause complaint, wait for the 20-day time period to expire. If the time period expires, move to have the lien discharged before making the decision to transfer the lien to a lien transfer bond.
  3. If recording a notice of contest of lien, wait for the 60-day time period to expire before taking action.

The reality is that the procedure implemented in this case should have been fine but for the application of the relation back doctrine that makes you say HUH?!?

As mentioned, if dealing with a lien, please make sure to discuss strategic considerations with a construction counsel that can help navigate the process and advise on the pros and cons.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

FORECLOSING JUNIOR LIENHOLDERS AND RECORDING A LIS PENDENS

When you foreclose on a construction lien, there are a couple of pointers to remember.

First, you want to make sure you include junior lienholders or interests you are looking to foreclose (or you want to be in a position to amend the foreclosure lawsuit to identify later).  The reason being is you want to foreclose their interests to the property. “[J]unior interest holders are a narrow class of mortgagees whose interest in the underlying property is recorded after the foreclosing contractor’s claim of lien is filed. This class is routinely joined to the construction lien enforcement action under section 713.26 to allow the construction lienor to foreclose out the junior lienholder’s interest in the property encumbered by the construction lien.” See Decks N Sunch Marine, infra.

Second, you want to record a lis pendens with the lien foreclosure lawsuit.  Failure to do so could be problematic because Florida Statute s. 713.22(1) provides in part, “A lien that has been continued beyond the 1-year period by the commencement of an action is not enforceable against creditors or subsequent purchasers for a valuable consideration and without notice, unless a notice of lis pendens is recorded.”

A recent case, Decks N Such Marine, Inc. v. Daake, 45 Fla.L.Weekly D1168b (Fla. 1st DCA 2020), discusses these pointers.  In this case, a contractor filed a construction lien foreclosure action in 2006 against residential real property. However, the contractor did not record a lis pendens until 2013.  The lis pendens, however, was recorded after the owner had a mortgage recorded on the property.  The contractor amended its construction lien foreclosure action to foreclose the mortgagee claiming the mortgagee was a junior lienholder.  The mortgagee moved for summary judgment pursuant to Florida Statute s. 713.22 arguing the lien was “not enforceable against creditors or subsequent purchasers for valuable consideration and without notice, unless a notice of lis pendens is recorded.”   In other words, the mortgagee was not a lienholder that could be foreclosed in light of the untimely recording of the lis pendens.  The mortgagee prevailed on this issue.

The mortgagee then sought its attorney’s fees against the contractor as the “prevailing party” under Florida Statute s. 713.29 (in Florida’s Lien Law).  The trial court agreed.  The appellate court did not.  The appellate court held that a junior lienholder is not entitled to attorney’s fees under Florida Statute s. 713.29 when prevailing in a construction lien enforcement action.  The contractor is not enforcing its lien against the junior lienholder but “joining it to the underlying action to ensue determination of superiority of liens or security interests upon a foreclosure sale.” Decks N Sunch Marine, supra.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

AN AMENDED LIEN DOES NOT DELAY THE 60 DAY WINDOW TO FORECLOSE A LIEN WHEN A NOTICE OF CONTEST OF LIEN IS RECORDED

imagesI previously discussed the value of an owner recording a Notice of Contest of Lien under Florida Statute s. 713.22 to shorten a lienor’s statute of limitations to foreclose a construction lien to 60 days from the date the lien is contested.   For more information on recording a Notice of Contest of Lien please look at this posting and this posting.

 

What happens if after a Notice of Contest of Lien is recorded the lienor amends its construction lien? For instance, say the following sequence occurs:

 

1:  Lien

2:  Notice of Contest of Lien

3: Amended Lien

 

Does an owner need to record another Notice of Contest of Lien for the Amended Lien?  If an owner does, then a lienor could extend its 60 day window to foreclose its lien by simply recording an amended lien.

 

This exact scenario was addressed long ago by the Florida Supreme Court in Jack Stilson & Co. v. Caloosa Bayview Corp., 278 So.2d 282 (Fla. 1973) which held that the foreclosure of an amended lien MUST still be brought within the 60 days from the initial Notice of Contest of Lien.  In other words, the recording of an amended lien does NOT toll (or stop) the running of the 60 day window to foreclose the lien when a Notice of Contest of Lien is recorded.

 

Therefore, if you are an owner, there is certainly a benefit to recording a Notice of Contest of Lien.  Conversely, if you are a contractor, do not think you can delay or escape the 60 day window to foreclose your construction lien if you received a Notice of Contest of Lien by simply amending your lien.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.