FRAUD CLAIMS AND BREACH OF WARRANTY CLAIMS AGAINST MANUFACTURER

A recent case touches upon two issues that are noteworthy when considering fraud claims and breach of warranty claims against a manufacturer. Below contains a discussion on these claims.

Independent Tort Doctrine

Florida’s independent tort doctrine provides that a party may not recover in tort for a contract dispute unless the tort is independent of any breach of contract.” MidAmerica C2L Inc. v. Siemens Energy, Inc., 2024 WL 414620, *6 (M.D.Fla. 2024).  This means tort allegations and claims MUST be separate and distinct from performance under the contract. Id. (citation omitted).

In MidAmerica C2L, a plaintiff sued a manufacturer relating to sophisticated equipment for a coal gasification plant. The parties entered into different agreements for the equipment and a license where the plaintiff could use the manufacturer’s patented technology for its coal gasification plants. A dispute arose and the plaintiff sued the manufacturer under various legal theories.  The manufacturer moved for summary judgment.

Two claims asserted against the manufacturer were grounded in fraudulent misrepresentation theories dealing with monetary damages and rescission of the contract. Both claims dealt with allegations that the manufacturer knew of defects in its equipment, had superior knowledge of the defects, had a duty to disclose the defects, and failed to do so. However, both fraud claims were a restatement of the SAME facts supporting the plaintiff’s breach of contract claims against the manufacturer. The trial court dismissed these claims because of the independent tort doctrine as the same material facts alleged in the fraud claims were alleged in the breach of contract claims.

Rescission

The trial court further found that the plaintiff’s request for rescission was not proper because “[the plaintiff] does not argue, much less demonstrate, that legal remedies are inadequate” to support the equitable relief of rescission.  MidAmerica C2L, supra, at *6.  The plaintiff attempted to counter by arguing that recission should be warranted because there was a lack of consideration for the contracts. This, however, was shot down because “Florida does not recognize the [equitable] claim of recission based on lack of consideration.” MidAmerica C2L, supra, at *7.  Florida law would recognize damages if there was a failure of consideration. Id. (citation omitted).

Breach of Warranty

Additionally, there was a worthwhile discussion on the plaintiff’s claim for breach of warranty of fitness for particular purpose against the manufacturer.  Although New York (not Florida) law governed this claim, it is still an important discussion for consideration, particularly since the analysis would be analogous under numerous jurisdictions.

The contract, as common, contained a warranty disclaimer which included a disclaimer for breach of the implied warranty of fitness for a particular purpose.

The elements for breach of implied warranty of fitness for a particular purpose are: (1) the seller, at the time of contracting, has reason to know the particular purpose for which the goods are required, (2) the seller has reason to know that the buyer is relying on the seller’s skill and judgment to select suitable goods for the specified purpose, and (3) the buyer did in fact rely on that skill or judgment. That said, a written disclaimer of a warranty of fitness for purpose precludes a party from relying on a representation that is specifically disclaimed in the agreement.

MidAmerica C2L, supra, at *3.

The warranty disclaimer should put the kibosh on this claim, right?  Well, the plaintiff argued that the warranty disclaimer is unconscionable and, thus, should be waived.  Under New York law, to argue unconscionability, the plaintiff must show the contract is both procedurally and substantively unconscionable when the contract was made. MidAmerica C2L, supra, at *4 (citation omitted). Regarding both procedural and substantive unconscionability, the court explained:

“[P]rocedural unconscionability considers whether there has been a lack of meaningful choice to accept a challenged provision by evaluating anumber of factors, including ‘(1) the size and commercial setting of the transaction; (2) whether there was a lack of meaningful choice by theparty claiming unconscionability; (3) the experience and education of the party claiming unconscionability; and (4) whether there was disparity inbargaining power.’ ” “[S]ubstantive unconscionability involves an analysis ‘of the substance of the bargain to determine whether the terms wereunreasonably favorable to the party against whom unconscionability is urged.’ ” “Procedural and substantive unconscionability have been described asoperating on a ‘sliding scale,’ meaning that ‘the more questionable the meaningfulness of choice, the less imbalance in a contract’s terms should be tolerated and vice versa.’ ”

MidAmerica C2L, supra, at *4 (internal citations omitted).

Regardless of the plaintiff’s unconscionability argument, the trial court still dismissed the claim.  The court found that this argument was simply based on the allegation that the manufacturer preyed on the plaintiff’s lack of bargaining power.  Besides, the plaintiff failed to identify any record evidence to remotely support its theory of unconscionability. “The Court finds that [the plaintiff] failed to plead unconscionability in the [complaint], and even if it had preserved this theory of recovery, there is no genuine issue of material fact relating to the applicability of the [warranty] disclaimer and the lack of unconscionability.” MidAmerica C2L, supra, at *5.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

SUBSEQUENT PURCHASER CAN ASSERT CLAIMS FOR CONSTRUCTION DEFECTS

Can a subsequent purchaser pursue construction defect claims relating to the original construction of the property?  This was the threshold issue on a motion for summary judgment by a drywall manufacturer against a subsequent purchaser of a home in Karpel v. Knauf Gips KG, 2022 WL 4366946 (S.D. Fla. 2022).  This matter deals with the defective Chinese drywall that was installed in homes years ago.  The plaintiffs, which were subsequent purchasers of a home, sued the manufacturer of the defective drywall for various theories including negligence, negligence per se, strict liability, breach of express and/or implied warranty, private nuisance, unjust enrichment, and Florida’s Deceptive and Unfair Trade Practices Act.

The trial court noted, from the onset, that Florida does NOT have a subsequent purchaser rule that prohibits subsequent purchasers from asserting construction defect claims. With this consideration in mind, the trial court went through the claims the plaintiff, as a subsequent purchaser, asserted against the manufacturer to determine whether they were viable claims as a matter of law.

Negligence Claim

The trial court found that a subsequent purchaser could sue in negligence.  “Florida courts have long allowed subsequent purchasers to sue for negligence including in construction defect litigation.”  Karpel, supra, at *2.

Negligence Per Se and Strict Liability Claims

The trial court held that the plaintiff’s negligence per se and strict liability claims were duplicative. Both could not stand; for this reason, the court entered summary judgment as to the duplicative negligence per se claim. “Strict liability means negligence as a matter of law or negligence per se, the effect of which is to remove the burden from the user of proving specific acts of negligence.Karpel, supra, at *3 (quotation and citation omitted).

A subsequent purchaser could pursue a strict liability claim against a manufacturer.  “[A] manufacturer is strictly liable in tort when an article he places on the market, knowing that it is to be used without inspection for defects, proves to have a defect that causes injury to a human being.”  Karpel, supra, at *4 (quotation and citation omitted).

Even Section 402A of the Second Restatement of Torts, adopted by Florida’s Supreme Court, provides: “(1) One who sells any product in a defective condition unreasonably dangerous to the user or consumer or to his property is subject to liability for physical harm caused to the ultimate user or consumer, or to his property, if (a) the seller is engaged in the business of selling such product, and (b) it is expected to and does reach the user or consumer without substantial change in the condition in which it is sold.” Karpel, supra, at *4.

There are, however, limits on strict liability.

First, Florida disallows recovery in tort where plaintiffs only claim economic losses such as ‘damages for inadequate value, costs of repair, and replacement of the defective product, or consequent loss of profits—without any claim of personal injury or damage to other property.Karpel, supra, at *4 (citation omitted).

Second, Florida courts will disallow recovery for strict liability where the purchaser was subject to the common law doctrine of caveat emptor.”  Karpel, supra, at *4.

Thus, a subsequent purchaser’s strict liability claim could be pursued against a manufacturer provided such damages are not barred by the economic loss rule or the doctrine of caveat emptor (which applies to commercial property and property purchased at judicial auction sales).  Karpel, supra, at *4.

Breach of Implied Warranty

The trial court found that a subsequent purchaser could NOT sue a manufacturer for breach of implied warranty.  “[I]t is abundantly clear that in cases like these, where no contractual relationship between a subsequent purchaser and a manufacturer exists, the former’s recourse is a claim for strict liability.Karpel, supra, at *4.

Breach of Express Warranty

While a contractual relationship is typically required for breach of express warranty, this requirement is relaxed if the express warranty is intended to benefit subsequent purchasers.  “A manufacturer’s liability for breach of an express warranty derives from, and is measured by, the terms of that warranty.”  Karpel, supra, at *4 (quotations and citation omitted).  However, in this case, plaintiff’s breach of express warranty claim failed because the plaintiff never introduced any express warranty into the record.

Private Nuisance

The trial court held that the subsequent purchaser could NOT pursue a private nuisance claim against the manufacturer.   To sustain a private nuisance claim, the plaintiff must prove that the defendant’s maintenance of the nuisance was the proximate cause of the plaintiff’s damages.  Karpel, supra, at *8.  “The Plaintiffs’ ownership and current control over the drywall conclusively forecloses them from arguing that the Defendants actively “maintain” the ‘nuisance’ they complain of.”  Id.

Unjust Enrichment

The trial court held that the subsequent purchaser could NOT pursue an unjust enrichment claim against the manufacturer.  An unjust enrichment claim requires the plaintiff to prove that the plaintiff conferred a direct benefit on the defendant. “The Plaintiffs conferred no direct benefit on the Defendant.” Karpel, supra, at *8 (finding that plaintiffs, as subsequent purchasers, obtained their homes from previous owners so the plaintiffs conferred no direct financial benefit on the manufacturer).

Florida’s Deceptive and Unfair Trade Practices Act (FDUTPA)

The trial court found that a subsequent purchaser could theortetically pursue a FDUTPA claim. “Because the law is clear that a plaintiff need not have actually relied on the purported deceptive or unfair practice, the Court’s analysis need not go further….The Plaintiffs’ status as subsequent purchasers does not foreclose them from arguing that the Defendants’ practices violated FDUTPA.”  Karpel, supra, at *9.

However, the trial court noted that actual damages under FDUTPA may implicate the economic loss rule because actual damages under the statute “are the difference in the market value of the product or service in the condition in which it was delivered and its market value in the condition in which it should have been delivered according to the contract of the parties.”  Karpel, supra, at *9 (quotation and citation omitted). For this reason, the court ordered the plaintiff and defendant to submit supplemental briefing because if the economic loss rule is implicated, the FDUTPA claim will fail (due to the same limitations relating to the strict liability claim).

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.