SUPREME COURT HOLDS ARBITRATOR CAN FULLY DECIDE THRESHOLD ARBITRABILITY ISSUE

shutterstock_1018025605The United States Supreme Court recently decided parties to a contract can agree, under the Federal Arbitration Act, an arbitrator, rather than a court, can fully resolve the initial arbitrability question.  Henry Schein, Inc. v. Archer and White Sales, Inc., 2019 WL 122164 (2019).  The arbitrability question is whether the dispute itself is subject to arbitration under an arbitration provision.  Parties that do not want to arbitrate try to circumvent this process by filing a lawsuit and asking the court to determine the threshold arbitrability question.  

 

In Henry Schein, Inc., the contract at-issue provided:

 

This Agreement shall be governed by the laws of the State of North Carolina.  Any dispute arising under or related to this Agreement (except for actions seeking injunctive relief and disputes related to trademarks, trade secrets, or other intellectual property) shall be resolved by binding arbitration in accordance with the arbitration rules of the American Arbitration Association.  The place of arbitration shall be in Charlotte, North Carolina.

 

The plaintiff in this case asserted a claim for injunctive relief (among other claims) and argued that, therefore, the dispute is not subject to arbitration based on the exception in the provision.  The initial, threshold issue became whether the dispute was subject to arbitration and, importantly, who decides this issue. The Court further looked at whether a trial court can resolve this issue under the “wholly groundless” exception, i.e.,the court can decide the issue if the argument for arbitration is wholly groundless.  

 

The Supreme Court held that, “[w]hen the parties’ contract delegates the arbitrability question to an arbitrator, a court may not override the contract.  In those circumstances, a court possesses no power to decide the arbitrability issue.  That is true even if the court thinks that the argument that the arbitration agreement applies to a particular dispute is wholly groundless.” Henry Schein, Inc, supra, at *4.  Through this ruling, the Court rejected the wholly groundless exception that would allow a trial court to rule on an threshold arbitrability question if the argument for arbitration is wholly groundless. 

 

The Court did not rule as to whether the arbitration provision at-issue delegated the arbitrability question to the arbitrator.   However, the American Arbitration Association’s rules provide that arbitrators have the power to resolve such threshold arbitrability questions so there is an argument that the provision through reference to the American Arbitration Association gave this authority to the arbitrator.  But, the best thing to do, as always, is to be clear.   Include language in the arbitration provision that specifically states that an arbitrator is authorized to decide the arbitrability of issues, particularly if it is your arbitration provision and you want disputes resolved by arbitration.  Conversely, if you want the initial, threshold issue of arbitrability to be decided by a court, make sure to specify that in the provision.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

 

 

 

 

QUICK NOTE: DO YOUR HOMEWORK WHEN IT COMES TO SELECTING YOUR ARBITRATOR

imagesMany construction contracts contain arbitration provisions.  Instead of litigating a dispute arising out of the contract, the parties will arbitrate the dispute per the arbitration provision.  There are advantages to arbitration and certain disputes bode well for arbitration.  The key is you want to make sure you select the RIGHT arbitrator or arbitrators.  Do your homework regarding the arbitrator list presented to you by, say, the American Arbitration Association.  Strike out those on the list that either do not have the requisite experience you need to decide the dispute or you believe they are not going to be impartial.  For instance, if you want an arbitrator that you think will specifically follow the letter of the law or the precise terms of a contract, select those on the list that meet this requirement; strike out others that do not.  The same philosophy would apply if you want an arbitrator to have specific factual knowledge or a factual understanding regarding a driving issue in the dispute.  Do not neglect the homework required to select –or try to select — the arbitrator you believe is the most qualified to understand the issues.

 

Now, why is this important?  It is important because you need to arbitrate a dispute with the understanding that the arbitrator’s award (decision) is FINAL.  There are no appellate rights.  None.  Vacating an arbitrator’s award is very challenging and the bases to vacate an award are limited and, most of the time, will NOT apply.

 

In a recent decision, a party tried to vacate an arbitration award.  One of the arguments was that the arbitration panel failed to follow  Florida law.   Well, guess what?  An arbitrator does not necessarily have to comply with Florida law.  Legal error by an arbitration panel is not a basis to vacate an arbitration award.  See Managed Care Ins. Consultants, Inc. v. United Healthcare Ins. Co., 42 Fla. L. Weekly D1599b (Fla. 4th DCA 2017).

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.