Let me
Represent YOUR
Construction
Interests!
Analyzing legal issues that
impact parties across the
construction industry.
Recent Posts
TAKEAWAYS FROM SCHEDULE-BASED DISPUTE BETWEEN GENERAL CONTRACTOR AND SUBCONTRACTOR
Posted on 10 August, 2024
A recent opinion out of the Southern District of Florida, Berkley Insurance Co. v. Suffolk Construction Co., Case 1:19-cv-23059-KMW (S.D.Fla. July 22, 2024), provides valuable takeaways on schedule-based disputes between a general contractor and subcontractor on a high-rise project.
In a nutshell, the general contractor’s original project schedule was abandoned due...
FIVE ISSUES TO CONSIDER IN GOVERNMENT CONTRACTING (OR ANY CONTRACTING!)
Posted on 20 July, 2024
The appeal of Appeals of – Konecranes Nuclear Equipment & Services, LLC, ASBCA 62797, 2024 WL 2698011 (May 7, 2024) raises interesting, but important, issues that should be considered. In this case, the government (in a supply contract) procured four portal cranes from the claimant. After an initial test of...
TIMELY AND PROPERLY ASSERT AFFIRMATIVE DEFENSES AND UNDERSTAND STATUTORY CONDITIONS PRECEDENT
Posted on 14 July, 2024
A recent case serves as a reminder to TIMELY and PROPERLY assert affirmative defenses and to understand statutory conditions precedent to construction lien claims. Failing to do one or the other could be severely detrimental to the position you want to take in a dispute, whether it is a lien...
QUICK NOTE: STAYING, NOT DISMISSING, ARBITRABLE DISPUTES UNDER FEDERAL ARBITRATION ACT
Posted on 23 June, 2024
As you hopefully know from posted articles, arbitration is a creature of contract. Stated differently, there must be a contractual basis to have a dispute resolved through binding arbitration. The Federal Arbitration Act (FAA) applies to transactions involving interstate commerce. Oftentimes, lawsuits are filed despite an arbitration provision in a...
DELAYS AND SUSPENSION OF THE WORK UNDER FIXED PRICE GOVERNMENT CONTRACT
Posted on 22 June, 2024
Here is an interesting fact pattern and case decided by the Civilian Board of Contract Appeals dealing with (1) force majeure type events and epidemics (Covid-19); (2) suspension of the work; and (3) delays. These are three topics important to all contractors including federal contractors.
In Lusk Mechanical Contractors, Inc. v...
About The Author
David Adelstein
Phone: (954) 361-4720
Email: Dadelstein@gmail.com
Pages
- About Me (David Adelstein)
- Bid Protests (Florida bid protests and Federal bid protests)
- Construction & Design Defects (and Florida Statutes Chapter 558)
- Construction Contracts
- Construction Liens
- Construction Safety, Workers Compensation Insurance, and Premise Liability Claims
- Delays, Acceleration, and Inefficiency (Lost Productivity)
- Insurance and Performance Bonds
- Payment Bonds Including Miller Act