There are literally some (or, perhaps, many!) disputes that will make you say “hmm!” The “hmm” is a euphemism for “what is a party thinking?!?” The case of Trump Endeavor 12 LLC v. Fernich, Inc., 42 Fla. L.Weekly D830a (Fla. 3d DCA 2017) is one of these cases because a party (the owner) is banking its defense on a technical “all-or-nothing” argument pertaining to whether a lienor (a supplier) substantially complied with Florida’s Lien Law because a supplier’s Notice to Owner identified the wrong general contractor. This is a challenging argument because the owner has to prove how they were adversely affected / prejudiced by the lack of substantial compliance, which is not an easy burden.
This case concerns the Trump National Doral Miami project. The project consisted of a lodge project and a separate clubhouse project, both of which had different general contractors. On the lodge project, the general contractor hired a painter which, in turn, procured paint from a supplier (the lienor). The supplier visited the project and obtained the Notice of Commencement from the owner so that it could perfect its lien rights. The owner furnished the supplier the Notice of Commencement for the clubhouse project that had a different general contractor. Relying on this Notice of Commencement, the supplier served a Notice to Owner. The Notice to Owner was timely serviced however it identified the wrong contractor – it identified the general contractor for the clubhouse project instead of the lodge project. Although the supplier later learned there was a different general contractor on the lodge project, it did not remedy the issue by serving a Notice to Owner on the correct contractor. Indeed, the contractor for the lodge project learned of the Notice to Owner furnished by the supplier and that the supplier was furnishing paint to the painting subcontractor for purposes of that project.
The supplier was owed approximately $32,000 and recorded a lien against the lodge project. The owner countered that the supplier did not have lien rights because its Notice to Owner incorrectly identified the wrong contractor. The supplier argued that it substantially complied with the Notice to Owner requirements and there was no prejudice to the owner as the result of it identifying the wrong contractor. The court sided with the contractor.
The court held that if the supplier substantially complied with the Notice to Owner requirements then such errors do not prevent its enforcement against a person who has not been adversely affected (prejudiced) by the error. Based on the facts, the supplier substantially complied with the Notice to Owner requirements and the owner could not establish how it was remotely prejudiced by the error.
Banking on certain technical arguments is literally banking on an “all-or-nothing” argument because if you lose that argument, then you lose the dispute and are likely liable for the prevailing party’s attorney’s fees. Here, the owner relied on a technical argument regarding the fact that the supplier failed to identify the correct general contractor on the Notice to Owner even though it knew the supplier was furnishing paint on the project. Why did the owner bank its entire case on such a technical position for an approximate $32,000 lien, especially when the owner could not prove how it was prejudiced by the supplier’s omission of the correct contractor? While there is strict compliance with the time requirements under Florida’s Lien Law, a party needs to substantial comply with other requirements. Substantial compliance will then shift the burden to the other party to prove how it was prejudiced by the substantial compliance versus strict compliance. This can be a heavy burden. Probably not worth banking an entire defense on this technical argument, particularly for a $32,000 lien.
Obviously, strict compliance is always best to avoid dealing with these technical arguments. For this reason, there is always value consulting with an attorney regarding perfecting and preserving your lien rights.
Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.