ACCELERATION COSTS MONEY


Contractors know or should know the concept of acceleration because acceleration costs money. Acceleration occurs when a contractor expedites its performance due to an excusable delay (a delay not its fault) in order complete its performance earlier than it would have considering the delay.

 

Contractors accelerate by incurring increased labor costs to work overtime and premium time (nights and weekends), adding more manpower, or adding more crews (which also may mean adding more supervision to supervise the additional labor). These added labor costs are typically direct payroll costs (factoring in labor burden) as well as equipment costs associated with operating the equipment (especially if it is owned equipment) for longer hours or renting additional equipment to be utilized by the additional manpower or crews. In addition, acceleration can result in inefficient labor hours because manpower is now working longer hours, new manpower is added and there is a learning curve associated with new manpower that is not familiar with the work, and the labor is potentially working under resequenced conditions and in congested locations with other trades. Thus, just because the contractor takes reasonable efforts to accelerate does not mean that it is incurring efficient / productive labor costs or that its acceleration efforts are substantially improving the completion date of the project.

 

There are two types of acceleration claims. The first type is the straightforward direct acceleration claim when the government/owner directs the contractor to accelerate its performance to finish the job in advance of the completion date. Many times, in this circumstance, the government/owner understands that it will need to compensate the contractor for the acceleration efforts.

 

Constructive acceleration is the other type of acceleration claim and the type more likely to lead to a dispute because the dispute centers around both entitlement and quantum. Constructive acceleration occurs where the contractor seeks additional time to complete the project due to what it claims are excusable delays, but the government/owner is unwilling to grant the contractor the additional time. To prove construction acceleration, the contractor needs to prove:

 

  1. there was a delay that was not its fault (an excusable delay) that impacted the completion date;
  2. the contractor notified the government/owner of the delay and requested additional time to complete its performance;
  3. the government/owner expressly directed the contractor to overcome the delay and complete the project in a shorter amount of time than the contractor was entitled to factoring in the delay or implicitly directed the contractor to overcome the delay through the refusal to grant additional time; and
  4. the contractor did in fact incur costs in accelerating its performance.

See Armour of America v. U.S., 96 Fed.Cl. 726, 757 (Fed.Cl. 2011) (“To prove a constructive acceleration claim, and entitlement to an equitable adjustment, which Armour [contractor] did not attempt to do during the proceedings before the court, a contractor must show (1) that the contractor encountered a delay that was excusable; (2) that the contractor requested from the government an extension of time due to the delay; (3) that the government denied the contractor’s request for an extension of time; (4) that the government demanded completion of the contract in a shorter amount of time than the contractor was entitled to, given the excusable delay; and (5) that the contractor was required to expend additional resources to adhere to the schedule on which the government insisted.”). See also Fraser Const. Co. v. U.S., 384 F.3d 1354 (Fed.Cl. 2004).

 

 

What is important to remember is not only will the contractor need to prove the excusable delay that impacted its schedule, but it will need to prove it notified the government/owner of the delay and requested additional time to perform which was denied. After proving all of this, the contractor will still need to establish that it actually accelerated its performance and incurred costs in doing so.

 

As a basic example, assume a project was to be completed December 31, 2014. This marked the date the owner needed to use the project for its intended purpose. However, due to excusable delays (assume many owner-directed change orders and/or design-related issues), this completion date is postponed a year to December 31, 2015. The contractor notified the owner of the delays and impacts to its schedule and requested an extension of time to complete the project; but, for whatever reason, the owner refused to grant additional time and implicitly demanded that the contractor complete the project on schedule. The contractor, as the result of the owner’s refusal to grant additional time, accelerated its performance to finish the project earlier than December 31, 2015 and to avoid the consequence of the owner assessing liquidated damages (i.e., the contractor accelerated to mitigate the impact of the delay). Based on the contractor and its subcontractor’s efforts, the project was completed on May 30, 2015–5 months after the original completion date, but 7 months before the contractor should have been complete considering the excusable delays. In this basic example, the contractor’s acceleration efforts mitigated the overall delay by approximately 7 months (the difference between May 30, 2015 and December 31, 2015) even though the contractor finished 5 months later than the original schedule. The contractor will need to prove the costs associated with these acceleration efforts.

 

It is good practice for contractors to work with attorneys and experts to preserve the acceleration claim and prove the excusable delays through a critical path schedule analysis and the costs incurred in accelerating performance.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

RECOVERING DELAY RELATED DAMAGES FROM PUBLIC PAYMENT BOND


One of the advantages to subcontractors of public payment bonds issued under the Federal Miller Act (or even the Little Miller Act) is that there is an argument for the recovery of unexecuted change orders and, and as it particularly pertains to this article, impact-related costs (whether delay or inefficiency / lost productivity). This should not be overlooked although language in the governing subcontract, etc. could dilute these arguments. However, having the argument and opportunity to recover impact-related costs from a payment bond is a huge upside.

 

If a subcontractor is owed money for inefficiency or delay, etc., and there is a public payment bond in place, it should not automatically forego pursuing these claims against the bond. Unlike a lien where these types of costs / damages are not lienable and could render an otherwise valid lien fraudulent in Florida, these are damages that could be pursued against a public payment bond. The subcontractor should carefully craft its argument in furtherance of maximizing its best chance to recover these types of damages.

 

For example, in the opinion of Fisk Elec. Co. v. Travelers Cas. and Sur. Co., 2009 WL 196032 (S.D.Fla. 2009), a subcontractor sought inefficiency / lost productivity damages against a payment bond surety that appeared to be issued under Florida Statute s. 255.05 (also known as Florida’s Little Miller Act). The payment bond surety moved to dismiss the subcontractor’s complaint arguing that these types of damages are not recoverable under the bond. The Southern District, relying on federal cases interpreting the Federal Miller Act, found that a subcontractor can pursue such damages against the payment bond for its out-of-pocket unreimbursed expenses. See, e.g, U.S. f/u/b/o Pertun Const. Co. v. Harvesters Group, Inc., 918 F.2d 915, 918 (11th Cir. 1990) (finding that subcontractor could recover under Federal Miller Act bond for out-of-pocket expenses resulting from prime contractor’s delay).

 

To maximize the recoverability for impact-related costs, the costs should be supportable costs that the subcontractor actually incurred in the performance of its contract work. Organizing the back-up supporting these costs and theory of the impact is critical and the subcontractor looking to pursue these costs from a public payment bond should consult counsel to best position its arguments to support recovery.  On the other hand, the prime contractor should ensure that its subcontract has contractual provisions that will make it challenging and provide hurdles for the subcontractor to recover such damages.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

SUPPORTING CONSTRUCTION DEFECT DAMAGES WITH AN ESTIMATE


One of the issues in construction defect disputes is whether the owner can prove damages with an estimate, which is often the case. Recently, in Kritikos v. John T. Anderson d/b/a Anderson Builders, et al., 38 Fla. L. Weekly D931a (Fla. 4th DCA 2013), the Fourth District Court of Appeals confirmed that an estimate as to the costs to repair construction defects can support a plaintiff’s (owner) damages. In other words, the plaintiff does not actually have to incur the costs to repair in order to be entitled to recover damages to correct a construction defect.

 
In this case, the contractor recorded a construction lien. The owner asserted, as a defense, that it is entitled to set-off the amount of the lien due to construction defects and delay-related damages. (The owner in this case ended up terminating the contractor when the project was substantially over budget and behind schedule.) It was the owner’s position that the defective work was subject to a design change so the measure of damages needed to be based on an estimate of what it would cost to complete the work (i.e., repair the defects) according to the original design / contract. The owner’s argument, as supported by the Fourth District, was based on precedent discussing an owner’s measure of damages when there is a construction defect, particularly the Florida Supreme Court decision of Grossman Holding Limited v. Hourihan, 414 So.2d 1037 (Fla. 1982) and the Second District Court of Appeals’ decision of Temple Beth Shalom & Jewish Center, Inc. v. Thyne Construction Corp., 399 So.2d 525 (Fla. 2d DCA 1981).  Both the cases of Grossman and Temple Beth Shalom maintain that the measure of damages when dealing with construction defects / unfinished construction contract is the reasonable cost to complete / repair per the original design / contract provided this does not result in economic waste. Kritikos, supra.

 
The key is that whether using an estimate or actual costs to support damages from a construction defect, the measure of damages is the reasonable cost to complete per the original design / contract (versus a subsequent and better design to repair the defects) provided that the repair costs do not amount to economic waste.

 
Interestingly, this case also discussed the owner’s set-off for delay damages. It is uncertain in this case whether the owner utilized any expert to establish delay damages, which is often and properly the case, or how the owner specifically presented the delay damages (as there is no discussion that there was a liquidated damages provision in the contract). The Fourth District simply stated: “Delay damages were properly presented to the jury. By their very nature, delay damages may not be subject to exact calculation, making the owner’s opinion of the value of his loss of use of his property admissible and relevant.” Kritikos, supra. Based on this limited statement, it would seem that these damages are not referring to liquidated damages or delays to the critical path of a construction schedule, but rather an owner (without any expert testimony) testifying as to “loss of use damages,” i.e., an owner testifying that due to the circumstances of the case, he/she was damaged by being not being able to utilize his residence. But, it is uncertain what the owner did to support these damages.

 

 

For more information on loss of use damages, please see: https://floridaconstru.wpengine.com/the-difference-between-lost-profit-and-loss-of-use-damages/

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.