ACCOUNT FOR THE IMPOSITION OF MATERIAL TARIFFS IN YOUR CONSTRUCTION CONTRACT

shutterstock_138974732After Hurricane Irma, I wrote an article that contractors should revisit the force majeure provisions in their construction contracts.  Not later.  But Now. The force majeure provision is an important provision in a construction contract to account for certain uncertainties that you have NO control over. 

 

Recently, another reason has given rise to contractors needing to revisit their force majeure provisions, as well as any provisions dealing with material escalations. Not later.  But now.  The imposition of raw steel and aluminum tariffs (tax on imported goods) and the back-and-forth regarding a potential trade war leads to the kind of uncertainty that should be assessed as a risk.  A risk in both time and cost from material escalations.

 

Contractors want to revisit their force majeure provisions, as well as any material escalation language, for these two reasons. 

 

First, you want to ensure any delay, to the extent there is any, associated with the tariffs or potential trade war provides for a time extension.    Any impact a contractor has with the delivery or fabrication of raw steel due to the imposition of tariffs should result in an extension of time.

 

 

Second, and probably the bigger concern, is associated with price.  Higher raw steel and aluminum costs could mean you based your price on inaccurate supplier and/or subcontractor pricing (pricing that did not factor in tariffs), particularly if the raw steel has not been pre-ordered or pre-delivered. Escalating material pricing is a concern.

 

 

Moving forward, I suggest including language in the force majeure provision that accounts for the imposition of tariffs and the concern of a trade war just to be safe.  Clarity in a contract is always better.  But, adding this language will account for time, but not the escalation of steel and aluminum pricing due to the tariffs.

 

If you are entering a lump sum contract, consider factoring this issue into your pricing.  Or, alternatively, identify an allowance associated with these materials so that you are not penalized based on actual pricing that accounts for the tariff   Another thing you can do is include a contingency in your lump sum contract with language that allows you to use the contingency for this purpose.  The difference between the allowance and contingency is there is still contractor-risk with the contingency if the costs exceed the contingency agreed upon in the contract.  Finally, you can include a carefully crafted material escalations provision that does not require you to bear the risk of certain material escalations.  

 

If you are entering into a Guaranteed Maximum Price (GMP) contract, you want to factor this escalating material pricing into the GMP cap.  Most GMP contracts have (and, if not, they should have) a line item for contingency.  The contingency amount should be increased (or there should be a separate contingency) to account for this issue with language that allows the contractor to use the contingency for escalating material pricing.  Alternatively, you can identify that due to the uncertainty associated with steel or aluminum pricing (or perhaps any other pricing) the GMP includes certain allowance items which will increase the contract through change order if the cost of the item exceeds the allowance. Finally, you can include a carefully crafted material escalations provision so that you are not bearing the risk of this uncertainty, i.e., material escalations entitle you to a change order. 

 

The politics behind the tariffs are irrelevant.  What is relevant, however, is the uncertainty behind the impact and pricing associated with the imposition of tariffs and the risk assessment that needs to be factored in to deal with this uncertainty.   This uncertainty affects the costs and potential time associated with obtaining raw materials to fabricate and incorporate into an owner’s construction project.

 

If this issue is currently impacting an on-going project, be proactive and consult an attorney that can review the language in your existing contract(s) and help, as need be, craft a change order request or claim based upon what has already been agreed to.

 

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

CONTRACTORS: REVISIT YOUR FORCE MAJEURE PROVISIONS TO ACCOUNT FOR HURRICANES

 

shutterstock_43059370We now know and can appreciate the threat of hurricanes.  Not that we did not appreciate the reality of hurricanes–of course we did–but Hurricane Harvey and Hurricane Irma created the type of actual devastation we fear because they hit close to home.  The fear came to life, creating panic, anxiety, and uncertainty.  It is hard to plan for a force majeure event such as a hurricane because of the capriciousness of Mother Nature.   But, we need to do so from this point forward.  No exception!  And, I mean no exception!!

 

A force majeure event is an uncontrollable event that cannot be anticipated with any degree of definitiveness.   The force majeure event will excusably delay or hinder performance obligations under a contract.  One type of force majeure event is a hurricane—an uncontrollable and unforeseen act of Mother Nature.   

 

Standard construction contracts will contain some type of force majeure language.  The language will entitle the contractor to an extension of time to perform since the force majeure event will have excusably delayed the contractor’s performance.  I am not going to rehash that standard language because this language needs to be modified and tailored to address the major risk of a hurricane.  Not only is time impacted, but money is impacted too.  We need to consider the total impact of a hurricane versus considering the impact in isolation or in a vacuum. 

 

Take a look at your present construction contracts.  Revisit the force majeure language.  Does this language adequately address the time and monetary impacts associated with a hurricane?  If it does, great!  If it does not, or can be written much better, now is the time to make this language a MUST-INCLUDED provision in your construction contracts because this risk is real.  It is not illusory and it will be a real risk during hurricane season.   If you do not know or are unsure as to the language, please engage a construction attorney to review your contracts or propose standard language for you catered to your business needs.  Even if you feel comfortable with the language, I would still encourage you to have a construction attorney review the language and provide constructive feedback on the language.  At this point, there is no excuse to neglect this risk or minimize the potential of a devastating time and cost impact.  Regardless of the type of construction work you perform, this risk needs to be addressed. Any owner should appreciate this risk because it is a reasonable risk that needs to be accounted for with certainty in your construction contract. Is this a risk you completely want to assume from a cost standpoint?

 

I have drafted numerous force majeure provisions tailored to the risks of a project and business objectives of a client.  I have drafted specific provisions or negotiated provisions dealing with the risk of a hurricane.   Based on this experience, here are my suggestions when considering the risk of a hurricane and the potential time and monetary impacts associated with the risk:

 

1)   Make sure there is builder’s risk insurance covering property damage during construction.  Builder’s risk insurance policies are specialized property insurance policies for construction projects.  Make sure the policy does not exclude hurricanes.  In other words, you do not want hurricanes to be an excluded peril, particularly if there is the chance your work will take place during the hurricane season and/or you are performing work where storm surge or flooding caused by a hurricane can be an issue.   If there is a sub-limit for hurricane-caused damage, know what that sub-limit is.   You want to know a) what property and materials will be covered for hurricane-caused damage, b) whether costs to protect the property and materials from the hurricane are covered, c) whether the policy covers repair costs, and 3) whether the policy covers delay-type damage caused by the hurricane.   Get a copy of the builder’s risk policy in advance.  This way you know whether or not you need to supplement the policy accordingly or, alternatively, you want specific perils covered before that policy is bound.  In fact, you will likely want to supplement this with a construction equipment / inland marine insurance policy.  Work with an insurance broker that has experience with construction projects to ensure you have the right insurance in place for the project and your business.

2)   Make sure your contract specifically identifies a named storm such as a hurricane as a force majeure event.  Make sure your contract specifically identifies a hurricane as a force majeure event.  Be specific.  A hurricane should be an event that entitles you to additional time to perform since time will be spent protecting the work and tying down equipment and materials, time will be spent dealing with the actual hurricane, and time will be spent assessing the damage, remediating the damage, and ramping back up. 

3)   Make sure your contact entitles you to delay-related compensation associated with a hurricane such as a force majeure event.  A time extension for a hurricane is a given.  But, what about compensation for the impact?  Your project schedule is not going to include the risk of a hurricane, as there is no reasonable way to include that time in a project schedule.  Hence, the time extension.   As we know though, time is money.  You want to include a provision that entitles you to compensation for the time impact.  The provision should entitle you to utilize contingency money for any delay or, perhaps more appropriately, entitle you to a change order for the time-related costs.  (I have even drafted provisions that include a specific force majeure contingency to address associated costs for a force majeure event.)  You can even stipulate to a daily rate for such time-impact costs (which I have also done) caused by a hurricane or force majeure event.  A hurricane will not only prevent you from performing, but it will shift your performance to essential activities (that will not be included in your schedule).  It is reasonable for impact-related costs to be recoverable for such a force majeure issue.  It is unreasonable for the risk to be entirely shifted to the contractor because Mother Nature is certainly a risk that a contractor cannot control.

4)   Make sure your contract entitles you to recover costs associated with preserving and protecting work in-place, materials, and equipment.  As mentioned, a hurricane will divert your performance to progressing the work to preserving and protecting work in-place, materials, and equipment.  All of this needs to be protected from prolonged, heavy wind activity, torrential rain, and potential surge and flooding.  There are costs associated with this and you want to make sure this is performed to minimize the likelihood of any loss.  You also want to make sure you have time to perform this work.  Be safe, rather than sorry, and do not wait to the last minute to see what direction the hurricane ultimately pursues.   Hurricanes, as we know, are unpredictable and take unpredictable paths.  We need to make sure we have time to not only preserve and protect the work, materials, and equipment, but that our employees and subcontractors (and their families) safely make the right decisions to protect their homes and families.  Similar to the above, make sure your contract specifies how you get paid for this type of work – whether through contingency funds or, perhaps more appropriately, a change order.  Notifying the owner in writing in advance of the protective measures being performed is always a good idea.  If the owner elects not to implement such measures because it does not want to bear the cost, then the owner is evidently bearing risk.

5)   Know your contractual notification requirements.  Your contract probably includes notification provisions to address time impacts and costs associated with protecting the work.  Make sure these provisions are reasonable in light of a hurricane or force majeure event.  Your priorities when dealing with a hurricane, in particular, will be shifted.  For this reason, you want to make sure the notification provisions are not unreasonably onerous and are more than reasonable to account for the issues you will be dealing with.  Think these issues through.  Remember, not only will you be dealing with the issues associated with the construction project, but there will be internal issues dealing with the safety of your employees, their families, and any subcontractors you hire.

 

 

Do not panic if your contract currently does not, in your opinion, sufficiently address all of these items.  You can address this moving forward.  You should address this moving forward.  Again, no excuses.  And, again, do not be reluctant to hire a construction attorney that can best protect your rights moving forward to account for this risk that we know is REAL.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

COMPLY AND UNDERSTAND CONTRACTUAL CONDITIONS PRECEDENT

shutterstock_463024297Contracts oftentimes contain conditions precedent to payment or another affirmative obligation.  The condition precedent needs to occur to trigger a party’s obligation to perform.  If the condition precedent does not occur, then the obligation to perform is never  triggered. 

 

Contracting parties need to understand and appreciate conditions precedent to perform in their contract.  This ensures that they perform a condition precedent to trigger another party’s obligation to perform or they know that their obligation to perform is not triggered until the opposing party performs a condition precedent.

 

The recent ruling in University Housing by Dayco Corp. v. Foch, 42 Fla. L. Weekly D1122a (Fla. 3d DCA 2017) exemplifies the importance of understanding conditions precedent to an affirmative contractual obligation.   In this case, parties entered into an agreement where party “A” was required to form a new development company and obtain financing to build a student housing complex.  Party “B”, when the financing (loan) was in place, was to transfer certain property to the newly formed development company.  Party A forming the new development company  and obtaining financing was a condition precedent to Party B transferring certain real property to the new development company.

 

Party A did not obtain the financing.  And, naturally, Party B did not transfer property to the new development company contending that the procurement of financing was a condition precedent to its obligation to transfer property.  The Third District, affirming the trial court, agreed with Party B that Party B’s obligation to transfer property to the development company was never triggered because Party A did not comply with a contractual condition precedent.  As the court summed up a condition precedent:

 

Under well established contract law, a condition precedent is a condition which calls for the performance of an act after a contract is entered into, upon the performance or happening of which its obligation to perform is made to depend…. Conditions precedent to an obligation to perform are those acts or events, which occur subsequently to the making of a contract, that must occur before there is a right to immediate performance and before there is a breach of contractual duty

University of Housing by Dayco Corp., supra (internal quotations and citations omitted).

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

WHICH CONSTRUCTION CONTRACT SHOULD I USE?

In the previous article I posted a chart that includes a side-by-side comparison of common risk allocation and risk assumption provisions in industry form construction contracts (the general conditions between the owner and contractor in the AIA, EJCDC, and ConsensusDocs industry form contracts).   This chart was used to illustrate various contractual provisions in industry form contracts in a presentation I recently did on construction contracts. The point of the presentation was to summarize many of the common risk allocation and risk assumption provisions in construction contracts that need to be considered when selecting and finalizing an industry form construction contract.  A portion of that presentation is below.  

 

[gview file=”https://floridaconstru.wpengine.com/wp-content/uploads/2016/10/Advanced-Construction-Contracts.pptx”]

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

INDUSTRY FORM CONTRACTS SERVE AS A TEMPLATE FOR YOUR CONSTRUCTION CONTRACT

Recently, I put on a presentation on construction contracts–considerations when using an industry form contract as the template for your construction contract.  There are good industry form contracts that contemplate many different project delivery methods and objectives.  These industry form contracts are promulgated by widely respectable organizations including the AIA, ConsensusDocs, EJCDC, and DBIA.  Based on your needs, these associations also promulgate industry form exhibits to use with your contract (e.g, payment application, schedule of values, payment bond, performance bond, dispute review board, electronic communications protocol, BIM, certificate of substantial completion, change order, construction change directive, green building, RFI, and many more!).    

 

Below is a chart I put together of a comparison of some of the common risk allocation provisions in the standard general conditions between an owner and contractor in the AIA, ConsensusDocs, and EJCDC as a frame of reference.  All of these standard form agreements serve as valuable templates, but they still require modifications based on the objectives of the parties and the preferred project delivery method.

 

[gview file=”https://floridaconstru.wpengine.com/wp-content/uploads/2016/10/AIA-Consensus-EJCDC-Comp..pdf”]

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

PRIME CONTRACT DRAFTING AND NEGOTIATION

Contract drafting and contract negotiation is important.  We all know that.  No surprises there!  But, when it comes to drafting a contract and negotiating terms and conditions, it is important to be fair and reasonable because a contract has to be an equally allocated give and take of risks.  A truly one-sided contract is more than often a recipe for disaster because it is unreasonable and written such that the other party is destined to fail.  

 

Ideally, the party best equipped to manage a risk should have responsibility in bearing that risk.    Every project is different (different client, price, scope, complexity, project delivery method, etc.) so there are different risk assessment considerations.  And, certain risks that you will assume in one contract does not mean you will assume the same risks in another.  

 

For me, when it comes to contract drafting and negotiation, I like to consult with the client to understand the dynamics of the project and risks the client foresees with the project.  This helps me appreciate the client’s business objectives relating to the project and the type of risks the client may be willing to fairly and reasonably assume.  I also start with a spreadsheet of those key issues prevalent in many construction contracts which may expand based on the client, price, scope, complexity, project delivery method, and other risk assessment issues pertinent to the project.  Below is an example of a spreadsheet of owner and contractor considerations with respect to the drafting and negotiation of a prime contract.  

 

[gview file=”https://floridaconstru.wpengine.com/wp-content/uploads/2016/08/Prime-Contract-Considerations.pdf”]

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

IS AN INITIAL DECISION MAKER, PROJECT NEUTRAL, OR DISPUTE RESOLUTION BOARD RIGHT FOR YOU?


Recently, I participated in a roundtable hosted by JAMS with experienced South Florida construction lawyers and retired circuit court judges to discuss the pros and cons of utilizing an initial decision maker (“IDM” and also referred to as a project neutral) or a dispute resolution board (“DRB”) to resolve disputes on construction projects.  The IDM and DRB are designed to resolve disputes, specifically claims (whether for time, money, or both), during construction to keep the project progressing forward without being bogged down by the inevitable claim.  There are numerous avenues to resolve disputes without resorting to filing a lawsuit or a demand for arbitration.   The thought is that dispute resolution will be facilitated by techniques designed to assist the parties with the resolution of claims during construction.  While direct discussions between the parties, meetings with the executives for business decision purposes, mediations, etc., are certainly helpful, sometimes these avenues are simply not enough to truly resolve a complex claim on a construction project that occurs during construction. 

 

This is where the IDM and DRB come into play.  Perspectives on the value of having an IDM or DRB and their defined roles are based on experiences.  But, what is important is that these experiences can help you determine whether an IDM or DRB is right for your project to resolve claims during construction and, if so, how you want to contractually frame the role of the IDM nor DRB.  As you know, the larger and more complex the project the greater likelihood that there will be disputes that occur during the course of construction.  Knowing this, how do you want these disputes to be resolved during construction, and who do you want to resolve these disputes, so that (a) the project continues to move forward notwithstanding such dispute, (b) the parties believe the agreed-upon resolution technique will truly assist them to resolve the inevitable claim without having to file a lawsuit or demand for arbitration down the road, and (c) the person (or persons) resolving the dispute is deemed as credible and objective.

 

For example, the American Institute of Architects (AIA) incorporates the concept of an IDM to its General Conditions (see A201-2007) as the person that renders initial decisions on claims.  If no person is selected as the IDM, the fallback is to have the architect serve in this role.  The IDM is tasked with reviewing the claim and can approve the claim, reject the claim, request additional data,  request a response to the claim, suggest a compromise, or advise the parties he/she is unable to render a decision on the claim.   The General Conditions further provides:

 

15.2.6.1 Either party may, within 30 days from the date of an initial decision, demand in writing that the other party file for mediation within 60 days of the initial decision.  If such a demand is made and the party receiving the demand fails to file for mediation within the time required, then both parties waive their rights to mediate or pursue binding dispute resolution proceedings with respect to the initial decision.  

See AIA-A201, s. 15.2.6.1.

 

The Consensus Documents (ConsensusDocs) incorporates the concept of a project neutral (similar to IDM) or DRB in its General Conditions if direct discussions between the parties reach an impasse. The General Conditions provide:

12.3.1 The Project Neutral/Dispute Review Board shall be mutually selected and appointed by the Parties and shall execute a retainer agreement with the Parties establishing the scope of the Project Neutral/Dispute Review Board’s responsibilities. The costs and expenses of the Project Neutral/Dispute Review Board shall be shared equally by the Parties. The Project Neutral/Dispute Review Board shall be available to either Party, upon request, throughout the course of the Project, and shall make regular visits to the Project so as to maintain an up-to-date understanding of the Project progress and issues and to enable the Project Neutral/Dispute Review Board to address matters in dispute between the Parties promptly and knowledgeably. The Project Neutral/Dispute Review Board shall issue nonbinding findings within five (5) business Days of referral of the matter to the Project Neutral, unless good cause is shown.

12.3.2 If the matter remains unresolved following the issuance of the nonbinding finding by the mitigation procedure or if the Project Neutral/Dispute Review Board fails to issue nonbinding findings within five (5) business Days of the referral, the Parties shall submit the matter to the binding dispute resolution procedure designated in Paragraph 12.5.  

See ConsensusDocs 200-2007, s. 12.3.1, 12.3.2.

 

If you like the concept of the IDM (project neutral) or DRB, then you need to consider whether you really want the architect or engineer of record to serve in any role, especially if you are the contractor.  As the contractor, your claims may derive from the contract documents and you probably want a more objective party to resolve such claims.  So the question becomes who do you trust to serve in this role?  A practicing construction attorney?  A mediator or arbitrator from a company like JAMS or the American Arbitration Association that has experience with alternate dispute resolution? An industry expert or experts that have no vested interest in the project other than to render initial decisions on claims?  Do you want a combination of all to serve on a DRB? Does this person(s) participate in project meetings? This is an important consideration. 

 

Next, what is the process you want the IDM or DRB to undertake to resolve claims?  This process is important from a timing standpoint and proof standpoint. Do you want the IDM or DRB to simply resolve claims on paper; in other words, render a decision by virtue of the claim submitted and any response provided?  Do you want the IDM or DRB to hear testimony from fact witnesses and, perhaps, experts?  Do you want the IDM or DRB to hear legal argument from counsel?  Do you want the IDM or DRB to have the authority to simultaneously examine experts to get at the heart of the truly disputed technical issues?  And, when do you want the IDM or DRB to step in and render an initial decision?  In other words, do you want direct discussions between the parties, mediation, a meeting with project folks, or a meeting with the business executives to take place first?  After the initial decision? Or never?

 

Then, what is the avenue you want to undertake if you want to contest (or appeal for lack of a better term) the IDM or DRB’s initial decision as to a claim occurring during construction? This is very important because let’s assume a party does not like the initial decision.  You want a mechanism to continue to discuss the claim and, perhaps, appeal the claim if discussions reach an impasse without that initial claim becoming binding.  The next step would naturally be binding dispute resolution, whether arbitration or litigation, to finally resolve the merits of the claim.   With this eventuality in mind, do you want the trier of fact (arbitrator, judge, or judge) to know that an IDM or DRB rendered an initial decision on this very issue and that decision was “x”?  This is an important consideration because human nature suggests that if the IDM or DRB is an objective party(ies) / industry professional(s), the fact that they rendered the initial decision of “x” will probably carry credibility with the trier of fact.  And, that credibility may be greater based on how the IDM or DRB rendered the decision.  Think about it.  If the decision was based on evidence or the consideration of testimony and experts, which may be analogous to the evidence and expert opinions presented at trial or arbitration, then it makes sense that the trier of fact is going to defer (perhaps unknowingly) to what the objective party / industry professional(s) decided regarding the claim.  Conversely, if the evidence and expert opinions are different than those presented to the IDM or DRB, does this alteration impact the credibility of the witnesses or the claim? Although, knowing this may make it less likely to actually pursue binding arbitration or litigation as to the claim considering the merits of the dispute had been decided by a knowledgeable / objective party(ies).

 

Finally, how is the IDM or DRB going to be funded – how are the costs of the IDM or DRB going to be budgeted and allocated?  This is another important consideration because this could be a costly endeavor. But, the costs may be worth it if the IDM or DRB is considered objective by the parties and the parties are truly engaged in the during construction dispute resolution techniques designed to avoid litigation or arbitration which could become more costly.  Also, the costs may certainly be worth it–the larger or more complex the project–when you know going into it that there will be claims and it is in the project’s best interest to promptly resolve the claims.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

 

PERSONAL GUARANTOR CANNOT ESCAPE A PERSONAL GUARANTEE BY…


In a prior article, I discussed the point that a personal guarantor cannot escape a contractual requirement of a personal guarantee merely by executing the guarantee as a corporate officer.   

The recent decision Frieri v. Capital Investment Services, Inc., 41 Fla. L. Weekly D1189a (Fla. 3d DCA 2016) illustrates this point.  In this case, a company hired an individual to help grow that company’s business.  The contract required the individual to invest $6 Million into a trust in consideration of the company’s president transferring substantial shares of the company into the trust.  The objective was that the trust would own the controlling shares of the company.  The money was transferred.  However, the shares were never placed in the trust and the trust never received controlling interest in the company.

 

The individual sued the company and the company’s president.  A judgment was entered against the company’s president and he appealed arguing there was no evidence to hold him personally liable.  The appellate court disagreed because the contract between the company and the individual imposed a personal obligation on the company’s president to actually place controlling shares into the trust and he failed to do so.  Although the company’s president signed the contract as a corporate officer of the company, his “official designation does not shield him from personal liability because the contract’s clear language shows that he assumed personal obligations [through the obligation to place the shares in the trust].” Fireri, supra

 

Remember, affixing a corporate title to a signature will not shield you as a personal guarantor if the contract clearly indicates language requiring a personal guarantee / personal liability.  And, as demonstrated in Frieri, personal liability can be assumed if the contract imposes an obligation on you to do something in a personal capacity, such as the obligation of the company’s president to specifically place shares in the trust.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

 

QUICK NOTE: DON’T NEGLECT CONDITIONS PRECEDENT TO PAYMENT IN YOUR CONTRACT

imagesThere is a good chance your contract contains conditions precedent to payment.  Such conditions precedent to payment include waivers and releases of lien (and, perhaps, claims) and contractually required warranties.  Make sure to comply with conditions precedent to payment!

 

In a case where a subcontractor sued a payment bond surety, the court held the subcontractor’s lawsuit was premature because the subcontractor did not comply with a condition precedent to payment, that being the submission of a release in satisfactory form.  Until such condition precedent was satisfied, payment was not due and owing the subcontractor.  

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

UNDERSTAND PROJECT DELIVERY METHODS SO THAT YOU SELECT A METHOD THAT BEST MEETS YOUR NEEDS

There are numerous project delivery methods or a method to deliver an owner the design and construction of a project.  Selecting a project delivery method requires the owner to consider many factors including the 1) project size, complexity, and scope, 2) insurance, 3) emerging technology such as building information modeling, 4) lean construction, 5) sustainability, 6) risk allocation, 7) control, 8) internal resources, 9) budget, 10) schedule, 11) contractor input during preconstruction, 12) risk allocation, 13) dispute resolution, and 14) collaboration amongst ownership, the design team, and the construction team. After carefully considering all of these factors, the objective is for an owner to select the project delivery method that will best bring it value including allocating responsibility of the design and construction to those best equipped to manage and handle that responsibility.  Learn more about the following project delivery methods by analyzing  considerations and perspectives of each method in the attached primer:

 

1. Design-bid-build

2. Multi-prime

3. Design-build

4. CM-agency

5. CM-at risk

6. Integrated project delivery

7. Public private partnership

[gview file=”https://floridaconstru.wpengine.com/wp-content/uploads/2016/02/Project-delivery-handout.pdf”]

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.